Now (Sept) thru the end of October - Plan, convert/create/update test scripts in ALM/QC, move pending support & project work into production
10/
...
08/
...
2015 - SAP release of year end base level support pack

...
10/
...
19/
...
2015 - End of day production snapshot to be used to refresh test environments
10/
...
19/
...
2015 - Development Freeze begins
10/
...
22/
...
2015 - Last date to implement support & enhancement changes until freeze ends on 12/
...
16/
...
2015
10/
...
23/
...
2015 - Unit test
11/
...
02/
...
2015 - System Integration Test (regression test fixes: 11/24-25
...
/
...
2015)
12/
...
11/
...
2015 - Go-live weekend!
12/
...
16/
...
2015 - Development Freeze ends