High-Level Timeline
...
Now (
...
August) thru the end of October - Plan, convert/create/update test scripts in ALM/QC, move pending support & project work into production

...
10/
...
02/2015 - Development Freeze begins
10/08/2015 - SAP release of year end base level support pack
...