Who | Yesterday | Today | Impediments | |
---|---|---|---|---|
Andrew | -- | -- | -- | |
Arnis |
|
|
| |
Cassandra |
| Sent out final version of Thalia "buzz card" - approved by Justin Parks; set up new user for testing- thalia1, ZINC meeting | Test Access control; wrote up test document for access control |
|
Hunter |
|
|
| |
Janet | nada | nada | will miss tomorrow's scrum for monthly IS&T leaders meeting, and Friday's scrum for mediation training | |
Justin | So many meetings. Didn't get anything Thalia done. |
| Kerberos meeting 2-3. Mobile Initiative meeting 4-5. | |
Qing | fixed th563 and th567 | training | training | |
Robin | Fixed: | Meetings (non-thalia) |
|
|
...
Who | Yesterday | Today | Impediments | |
---|---|---|---|---|
Andrew | Finish new UI build/inclusion system for IME. | -- | Other work. | |
Arnis |
|
| no scrum today - meeting | |
Cassandra |
| worked on "buzz card" design, consulted with Justin Parks; tested upload and access control | get approval for "buzz card"; testing |
|
Hunter |
|
|
| |
Janet | got reply from Michael Dutton | check in with Leah re: help | not much unscheduled time this week | |
Justin | Had a couple of phone chats with Victor Park of PSB. PSB has decided on co-branding design that I think we can be happy with. Victor should have a mockup of that to us sometime today. | All-day Kerberos meeting. | not at scrum today - All-day Kerberos meeting | |
Qing | fixed th-546 | training | training class Tue-Friday | |
Robin |
| Zinc team meeting |
|
...
Who | Yesterday | Today | Impediments | |
---|---|---|---|---|
Andrew | Clean up IME build. | Implement new UI build. | Other work. | |
Arnis |
|
|
| |
Cassandra |
| created two designs for "buzz card" | continue with Thalia "buzz card" design; send design to thalia-dev for review |
|
Hunter |
|
|
| |
Janet |
|
| training class taking up unscheduled time | |
Justin | code freeze | talk with psb about logo. fix sprint 4 regressions | snow snow everywhere | |
Qing | stoodby when Janet released to QA | bug fixes |
| |
Robin | Downloadable slideshow completed | Release to QA with downloadable slideshows |
|
...
Who | Yesterday | Today | Impediments |
---|---|---|---|
Andrew | Informal meeting to develop some new build system ideas. | Implenent same. | Other work. |
Arnis |
|
|
|
Cassandra |
| testing of new release |
|
Hunter |
|
|
|
Janet |
| build and release to QA |
|
Justin |
|
|
|
Qing | worked with Robin to build and run thalia locally | standby incase Janet has questions on build |
|
Robin |
|
|
|
...
Who | Yesterday | Today | Impediments |
---|---|---|---|
Andrew | More time retweaking the build system at Qing's request. | -- | Other work; no real time for non-critical Thalia work for the rest of this week. |
Arnis |
| testing |
|
Cassandra |
|
|
|
Hunter |
|
|
|
Janet |
| none today | no scrum today |
Justin |
|
|
|
Qing | 1. th-524 | 1. test more |
|
Robin | TH-477 >10 freeform tags error message should remain visible longer (currently disappears after 5 sec) | Finish access control issues |
|
...
Who | Yesterday | Today | Impediments | |
---|---|---|---|---|
Andrew | -- | -- | -- | |
Arnis |
|
|
| |
Cassandra |
| worked through release notes, tested, closed fixed bugs, tested new Upload UI. Uploaded QuickStart, asked for feedback, began "buzz card". | After feedback about the QuickStart video, worked on understanding output options, spent time fiddling with QuickStart - determined that UI changes require it to be redone. |
|
Hunter |
|
|
| |
Janet | replied to mdutton re:usability schedule | Thalia bus. meeting with Wilson, Pat, and Catherine | missing scrum tomorrow | |
Justin |
|
|
| |
Qing | finished code and model change to add a hascustompermission attribute to item all-hands meeting | review and test code |
| |
Robin | TH-401 Album shows "Preview not Available" for items deleted from Library - should show "Item not available" | access controls |
|
...
Who | Yesterday | Today | Impediments | |
---|---|---|---|---|
Andrew | Worked with Qing to iron out some tomcat deployment problems, yammered with people a bit about builds. | -- | Other work. | |
Arnis |
|
|
| |
Cassandra |
| general testing | consulted with Catherine, Bryan about "buzz card"; uploaded QuickStart to locker - needs an index page, uploaded it to personal space so people could review it. |
|
Hunter |
|
|
| |
Janet | sent Leah techwriting details | reply to Usability testing mail - yes on 1/29-1/31 | meetings | |
Justin | Finished up upload work for sprint 4. | Release to QA. Slideshow work. | All-day Kerberos meeting. | |
Qing | test and document new code | add a hascustompermission attribute to item |
| |
Robin | TH-495: "More" button for Advanced Search does not clear previous search terms | Check access control rules for each item when dragging to a slideshow or album |
|
...