        The 12m signal chain installation / checkout is on schedule.

        1) All of the signal chain systems (frontend and backend) were installed by 1/21
        2) Frontend / Backend Integration completed 1/25
        3) Have begun signal chain integration testing and verification (estimated completion 2/5)

                                                                                                                                                                                                                                                                                                                                                             Chet Ruszczyk - 27 Jan 2016

Wettzell

Ishioka

  1. Operation of Ishioka antenna is now under interruption because of construction of operation building, and will resume after April. 
  2. Modification of cryogenic dewar for QRFH system is being done. 

...