Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

If you want to add a comment or see the comments that have been made you have the ability to click on the comments tab.  In addition, any documents, another form or another process can be attached in the following tabs.

Anchor
Schedule
Schedule
Schedule

The schedule module will be used to track the project schedule.  A template has been created for consistency across projects and ease of use.  The following are the steps you will take when you first start using the schedule:

...

You may also want to save Snapshots so you can compare current schedule to prior Snapshots and/or the Schedule Baseline 

Activate and Save Baseline

...