The schedule module will be used to track the project scheduleManage and track project schedules using the Schedule module.  A template has been created for to promote consistency across projects and ease of use across all MIT Facilities projectsThe following are the steps you will take when you first start using the scheduleWhen you begin using schedules:

  1. Adjust the durations and dates to fit the project.

  2. Activate the schedule.

  3. Save Baseline of the schedule tasks.

  4. Update and maintain the schedule.

Updating Schedule

The steps to updating the schedule are the same for when you first setup the project schedule to when you are maintaining the project schedule. 

 

To update the schedule you will click the Pencil icon, update dates or the duration and click the Save icon.

 

Click on the Pencil icon to update the schedule. The icon changes to allow users to save the change or to cancel the action.

It is good practice to save Snapshots of the schedule. You may save a Snapshot by using the Save Snapshot choice on the Actions dropdown menu that is located next to the Update Schedule button. You can use Snapshots throughout the life of the project to compare the You may also want to save Snapshots so you can compare current schedule to prior Snapshots and/or the to the Schedule Baseline.

Activate and Save Baseline

...