Manage and track project schedules using the Schedule module. A template has been created to promote consistency and ease of use across all MIT Facilities projects. When you begin
Begin using schedules by:
Adjust the Adjusting durations and dates to fit the project.
Activate the schedule.
Save Baseline of the schedule tasks.
for your projects
Activating schedules.
Saving schedule baselines
Frequently updating and maintaining schedules for all of your projectsUpdate and maintain the schedule.
Updating Schedule
Click on the Pencil icon to update the schedule. The icon changes to a disc and an "X" to allow users to save the change or to cancel the action.
It is good practice good project management practice to save schedule Snapshots of the schedule. You may save . Save a Snapshot by using the by picking Save Snapshot choice on from the Actions dropdown menu that is located next to the Update Schedule button. You can use Use Snapshots throughout the life of the project your projects to compare the current schedule to prior Snapshots and/or to the Schedule Baseline.
Activate and Save a Baseline
Activing a schedule makes it available for all users to see. Before the schedule is activates only Prior to activation only the e-Builder Administrator and the Schedule Manager have the ability to see itcan see the schedule.
To activate the schedule select all tasks with the first checkbox and go to Actions – Activate with check box located in the grey table header. Choose Activate from the Actions dropdown menu that is next to the Add Task button.
Once you have activated the schedule, select all the tasks again, click the Action button and select Save Baseline.
...