Summary

  • The Project Definition Form Creation Process results in additional project information being added to e-Builder.
  • The primary actor is the CC Planner.
  • The planner may work collaboratively with the Project Manager, SEG, Assessor or others while facilitating the addition of the PD form into e-Builder.
  • As a result of this process the CRSP Screening Process is spawned.
Column
width50%

 Process Map

Click to enlarge

 

...