Project Managers manage and track project schedules using the Schedule module.

The Schedule module is used to track project schedules.

Image Added

A template has been created to promote consistency and ease of use across all MIT Facilities projects. The template will be visible when you begin using the Schedule module. If the template does not appear please contact the e-Builder administrator.

The template accounts for Design, Construction, Commissioning and Turnover and Occupancy

Begin using schedules by:

.

Take these steps when you start using the schedule.

  1. Adjust Adjusting durations and dates for to fit your projects

  2. Activating schedules.

  3. Saving schedule baselines

  4. project.

  5. Activate the schedule.

  6. Save a baseline of the scheduled tasks.

  7. Update and maintain the schedule.Frequently updating and maintaining schedules for all of your projects

Updating Schedule

Click on the Pencil icon to update the schedule. The icon changes to a disc and an "X"  to allow users to save the change or to cancel the action.

...