Actors and Actions

Following needs identification, discussions and approval of the project by the Working Committee, the DoF Planner adds the PD Form in e-Builder. It is reviewed by the Program Manager and the Planning Manager and is approved in its final form by the Working Committee.
ActorAction

CC Planner, CC Planning Manager, eB Admin, PM, R&M Manager, Utilities Program Manager 

Can initiate this process
CC Planner, CC Planning Manager, Project ManagerCan view drafts of this project
CC Planning Manager, CRSP Admin, eB Admin, Program ManagerCan view all process instances
All UsersCan report on this process, are notified as process moves through steps
Column
width50%

e-Builder Steps

To complete the process in e-Builder:

  1. Log into e-Builder and open the project.
  2. Select Processes from the Project Menu on the left side of the page.
  3. Click the Start Process button in the upper right portion of the page.
  4. Click the 02.02 - Project Definition Form Creation (PD) process link.
  5. Complete the form.
  6. If you are finished with the form, and wish to Submit it to the workflow step or Actor, click the Submit button.
  7. If you are not finished with the form, and wish to save a partially completed form, the Save Draft button.
Tip
titleHints and Tips