If you have already opened your project you may open the schedule by click clicking the Schedule link in the left- side Project Menu. After clicking the link the Schedule Details page appears.
...
Do not remove any of these tasks. You may update that the schedule by adding tasks.
Adding a Task
Click the Add Task button to add a
...
task. The Add Task page appears.
Though other options are available you will likely add a task as a subset of one of the existing tasks in the MIT template. To do so choose the Add as a subtask of radio button and select the parent task.
Other options include Master Task, Task Name, Type, Description, Draft, Milestone, Resource, Manager, Constraint Type, Constraint Date, Duration, Approval Required for Date Changes and Approval Required for % Complete Changes.
You will also be able to set Predecessors, Lag and Link Type
example measure windows under design
Draft vs ???
Print GANT?t
Export and Import to MS Project???
...