The Schedule module is used to track project schedules.
Scheduling gives program managers, project managers and project participants a single system to coordinate people and their activities.
A template, designed for MIT projects, is provided to promote consistency at the highest schedule "level" A template has been created to promote consistency and ease of use across all MIT Facilities projects. The template will be visible when you begin using the Schedule module for your project. If the template does not appear please contact the e-Builder administrator.
The template accounts for Design, Construction, Commissioning and Turnover and Occupancy.
Take these steps when you start using the schedule.
...
Adjust durations and dates to fit your project.
...
Activate the schedule.
...
Save a baseline of the scheduled tasks.
the follow high level schedule activities:
- Design
- Scoping
- Procurement Services
- SD
- DD
- CD
- Construction
- Commissioning and Turnover
- Occupancy
...
Opening a Schedule
If you have already opened your project you may open the schedule by clicking the Schedule link in the left- side Project Menu. After clicking the link the Schedule Details page appears.
...
Click the Save Button to save any changes.
Take these steps when you start using the schedule.
Adjust durations and dates to fit your project.
Activate the schedule.
Save a baseline of the scheduled tasks.
Update and maintain the schedule.
Updating a Schedule
Click on the Pencil icon to update the schedule. The icon changes to a disc and an "X" to allow users to save the change or to cancel the action.
...