Scheduling gives program managers, project managers and project participants a single system to coordinate people and their activities as pertains to projects.A template, designed for MIT projects, is provided project tasks.
Schedules typically follow this general path:
- The e-Builder admin, when creating the project in e-Builder, applies an MIT-specific template to the project schedule to promote consistency at the highest schedule/task "level" and to ease of use
...
- .
- Schedule/Project managers update tasks within the new schedule by adjusting dates and/or adding new subtasks .
- The status of the schedule is changed from Draft to Active.
- A baseline is saved.
- A snapshot of the baseline is saved.
- Resources update their progress for individual tasks.
- Schedule/Project Managers approve changes as required and continually update the schedule as needed.
The template accounts for the follow high level schedule tasks:
- Design
- Scoping
- Procurement Services
- SD
- DD
- CD
- Construction
- Commissioning and Turnover
- Occupancy
Working with Schedules will require that you add tasks below those that appear in the template and that you adjust the timing of all tasks.
Opening a Schedule
Open the Schedule from an open project by clicking the Schedule link in the left- side Project menu or click on the Schedule tab to open the module and then select a project using the Project drop down menu.
...
Click the Save Button to save any changes.
Take these steps when you start using the schedule.
Adjust durations and dates to fit your project.
Activate the schedule.
Save a baseline of the scheduled tasks.
Update and maintain the schedule.
The template accounts for the follow high level schedule tasks:
- Design
- Scoping
- Procurement Services
- SD
- DD
- CD
- Construction
- Commissioning and Turnover
- Occupancy
Working with Schedules will require that you add tasks below those that appear in the template and that you adjust the timing of all tasks.
Updating a Schedule
Click on the Pencil icon to update the schedule. The icon changes to a disc and an "X" to allow users to save the change or to cancel the action.
It is good project management practice to save schedule Snapshots. Save a Snapshot by picking Save Snapshot from the Actions dropdown menu that is located next to the Update Schedule button. Use Snapshots throughout the life of your projects to compare the current schedule to prior Snapshots and/or to the Schedule Baseline.
Tasks
Tasks appear in the bottom half of the Schedule Details page. The MIT Project Schedule Template displays 9 tasks.
...