Schedules give program/project managers and project participants a single system to coordinate resources and their , project tasks and milestones.

...

WhoEvent
e-B adminWhen the project is added to e-Builder , the e-Builder admin applies an MIT-specific template to the project to establish consistent high level tasks across all e-Builder projects. The use of a template helps ensure consistency at the highest task level also promotes ease of useacross all projects in the e-Builder portfolio.
Schedule/Project Managers
  • Update tasks for the new schedule by adjusting dates or adding tasks below the high level template tasks.
  • Change the status of the schedule from Draft to Active
  • Save a Baseline
  • Save a Snapshot of the baseline
  • Approve changes made to the schedule
Project Resources (participants)Update the schedule for their individual tasks

...