Wiki markup without migration | h1. Start {:id=Start}
{cloak:id=My Cloak|visible=true}
Started by the CC Planner, CC Planning Manager, eB Admin, Project Manager, R&M Manager, UTLITIES-Program Manager. They will fill out the required field and take the following action:
Submit
Status of Process: Submitted
Causes Field Validation: Yes
If initiated by CC Planner, process routes to Project Manager Review
If not initiated by CC Planner, process routes to CC Planner Completes PD Form
.
{cloak} Started by the CC Planner, CC Planning Manager, eB Admin, Project Manager, R&M Manager, UTLITIES-Program Manager. They will fill out the required field and take the following action: Submit Status of Process: Submitted Causes Field Validation: Yes Start by the CC Planner, CC Planning Manager, eB Admin, Project Manager, R&M Manager, UTLITIES-Program Manager Cloak |
---|
They will fill out the required field and Submit. Following submission:
The status of the Process is Submitted Field Validation takes place.
If the process was initiated by CC Planner, the | If initiated by CC Planner, process routes to Project Manager Review |
. If not initiated by CC Planner, process routes to CC Planner Completes PD Form | CC Planner Completes PD Form Cloak |
---|
CC Planner reviews the process and complete the required fields. | One of the following actions will be taken: Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: Project Manager Review
Revise Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: Initiator Review
Void Status of Process: Void Causes Field Validation: No Add Comments: Yes, Required Next Step: Finish
|
Project Project Manager Review Cloak |
---|
Project Manager reviews the process and completes the required fields. They will take one of the following actions: Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: Planning Manager and Prog. Manager Review
Revise Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: CC Planner Revise
|
Initiator Review Cloak |
---|
Process Initiator reviews the process and completes the required fields. They will take the following action: Reply Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: CC Planner Completes PD Form
|
CC Planner Revise Cloak |
---|
CC Planner reviews the process and completes the required fields. They will take the following action: Resubmit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: Project Manager Review
|
Planning Manager and Prog. Manager Review
- Project Manager and Program Manager review the process and complete the required fields. They will take one of the following actions:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Number of Actors Required to Complete: All Next Step: Working Committee Review
Revise Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: CC Planner Revise
- Working Committee Review
- CC Planning Manager will review the process with working committee outside of e-Builder then complete the required fields. They will take one of the following actions:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Number of Actors Required to Complete: All Next Step: Utilities , O&M, and SEG Review
Put on Hold Status of Process: On Hold Causes Field Validation: Yes Add Comments: No Next Step: Finish
- Utilities , O&M, and SEG Review
- Utilities Director, O&M Director, and SEG Assignor will review the process, add their comments and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: No Add Comment: No Number of Actors Required to Complete: All Next Step: CC Director, Ops, and M&U Review
- CC Director, Ops, and M&U Review
- CC Director, M&U Director, and IBO Director will review the process, add their comments and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: No Add Comment: No Number of Actors Required to Complete: All Next Step: CRSP Screening Review
- DoF Planning Manager (Governance)
- CC Planning Manager will review the process, add their comments, prepare the Capital Renewal List for the RCRSP agenda, and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: No Add Comment: No Next Step: Spawn Team Assignment
- Spawn Team Assignments
- When the Submit action is taken from the DoF Planning Manager step, the process will proceed to this spawn step. In the spawn step the 02.01 – Team Assignment process will be started and moved to the first step of that workflow. The following action will be automatically be taken after:
Spawn Complete Spawn Process: 02.01 – Team Assignment Spawn Process Initiator: Automatically Spawned Attach Process: Yes Copy Attached Files: Yes Next Step: Finance Office Issues IO Number
- Finance Officer Issues IO Number
- Financial Officer will review the process, add the Cost Object Number, and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comment: No Next Step: Apply Funding
- Apply Funding
- Financial Analyst will review the process, apply funding, and take the following action:
Submit Status of Process: Approved Causes Field Validation: Yes Add Comment: No Next Step: Finish
- Finish
|