For the duration of the development freeze (10/15/2016-12/87/2016), a special development process should will be used for development of fixes to SAP. The aim of this process is to avoid the introduction of non-support pack changes into the Support Pack test system (SH2) or the Production system (PS1).
...
All transports must be associated with a Request Tracker (RT) ticket recorded in the RT SAP::Test Issues queue under the project name 'SAP Support Pack 2015Packs 2016'. Note: Any in-process changes saved during step 1 will need to be manually merged into the corrected objects after the development freeze.
...
Transports generated during Unit Testing will be accumulated and moved as a group as part of the Support Pack application process in to the test system, SH2.
Transports generated during SIT will be imported into SH2 twice a day (shortly after 12 noon and then again after 5pm). Requests must be received by 11:30am and 4:30pm, respectively.
These transports must be associated with RT tickets recorded in the Request Tracker SAP::Test Issues queue under project name "SAP Support Pack 2015Packs 2016".
Transport path = SF2 -> SH2
Approver: Frank Quern
...