High-Level Timeline
...
September thru the end of October - Plan, convert/create/update test scripts in ALM, move pending support & project work into production
...
10/
...
12/
...
2017 - SAP release of year end base level support pack
...
10/13/
...
2017 - Last date to implement support & enhancement changes until freeze ends on 12/07/
...
2017
...
10/
...
16/
...
2017 - Development Freeze begins
...
10/
...
16/
...
2017 - End of day production snapshot to be used to refresh test environments (9/
...
18 for SF3)
...
10/
...
23/
...
2017 - Unit test
...
10/30/2017 - 10/31/2017 Controlled Payroll Runs (SH2)
11/01/
...
2017 - System Integration Test (regression test fixes: 11/21-22
...
/
...
2017)
12/
...
01/
...
2017 - Go-live weekend!
12/
...
06/
...
2017 - Development Freeze ends