High-Level Timeline (**proposed**)
...
September thru the end of October - Plan, convert/create/update test scripts in ALM, move pending support & project work into production
...
11/01/2017 - System Integration Test (regression test fixes: 11/21-22/2017)

12/01/2017 - Go-live weekend!
...