  • This process is usually initiated by the CC planner or the project manager. Other roles with the ability to being the process are:
    • CC Planning Manager
    • R&M Manager
    • UTLITIES-Program Manager
    • e-B Admin
  • When not started by the CC planner the process routes to the CC planner as the second step.
  • After the PD form is completed this process spawns the 03.01 Milestone Project Budget Estimate process.
Card
labelProcess Map
This process map reflects the process in the production environment as of March 5, 2018.
Image Modified
Card
labelStep Descriptions

Toggle Cloak
1. Start

Cloak
  • If the process was initiated by CC Planner, the next step is Project Manager Review.
  • If not initiated by CC Planner, the next step is CC Planner Completes PD Form.

Toggle Cloak
2. CC Planner Created?

Cloak
  • If the initiator is the CC Planner the next step is Project Manager Review.
  • If the initiator is not the CC Planner then the next step is CC Planner Completes PD Form.

Toggle Cloak
3. CC Planner Completes PD Form

Cloak
  • CC Planner reviews the process, completes the required fields and selects one of the following actions: Submit, Revise or Void.
  • If Submit is chosen the next step is Project Manager Review.
  • If Revise is chosen the next step is Initiator Review.
  • If Void is chosen the next step is Finish.

Toggle Cloak
 4. Project Manager Review

Cloak
  • The Project Manager reviews the process with the option to approve and Submit or to Revise.
  • To approve and submit the project manager must complete the required fields including section 9.1 on the process form by choosing the date.
  • If Submit is chosen the next step is Planning Manager and Prog. Manager Review.
  • If Revise is chosen the next step is CC Planner Revise.

Toggle Cloak
5. Initiator Review

Cloak
  • The process Initiator reviews the process, completes the required fields and clicks Reply.
  • The next step is CC Planner Completes PD Form

Toggle Cloak
6. CC Planner Revise

Cloak
  • The CC Planner reviews the process, completes the required fields, and clicks Resubmit.
  • The next step is  Project Manager Review

Toggle Cloak
7. Planning Manager and Prog. Manager Review

Cloak
  • Project Manager and Program Manager review the process, complete the required fields and choose to Submit or Revise.
  • If Submit is chosen the next step is Working Committee Review
  • IfRevise is chosen the next step is CC Planner Revise

Toggle Cloak
8. System Starts (spawns) 3.01 Milestone Project Estimate process

Cloak
  • The budget process is started.
  • The project manager attaches the budget request spreadsheet requesting the Capital Renewal funding.

Toggle Cloak
9. Working Committee Review

Cloak
  • The working committee reviews the budget request

Toggle Cloak
10. Utilities, O&M and SEG Review

Cloak
  • Utilities Director, O&M Director, and SEG Assignor review the process, add their comments and click Submit.
  • The next step is Create PD Form

Toggle Cloak
11. CC Director, Ops and M&U Review

Cloak
  • Review step for the CC Director, Ops and M&U Review

Toggle Cloak
12. Create PD Form (Mail Merge Step)

Cloak
  • The PD form is created and stored in the Documents folder.
  • Next Step: One Funding Source? (Conditional)

Toggle Cloak
13. CC Planning Manager Hold - Record Approvals

Cloak

The approved Capital Renewal allocation is recorded.

Toggle Cloak
14. Create Final PD Form

Cloak

e-Builder creates the final PD form.

15. Finish

Card
idTRPD
labelTraining Material

 

PDF
namePD Form and MPEB.pdf

...