Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Sprint phase:

Sprint 5 - Release eng: Robin

Next Sprint

 sprint planning preparation

  •  product product owner picks focus, features, and bugs for next sprint, moves to a new sprint bucket in JIRA
  • all: may nominate candidate bugs and features for sprint

 

 

 sprint planning meeting

  • all: look at sprint bucket in JIRA and make estimates for their tasks
  • Product Owner prioritizes items for planned work.

 

 

 sprint planning meeting

  • Choices for planned work are reviewed by team.
  • release engineer chosen

2/11

 

sprint begins

  • dev: starts coding
  • qa: starts testplans
  • scrum master: produces burndown chart
  • ongoing releases to test environment as needed, to be negotiated between dev and QA

2/12

 

 new features/planned work completed

  • release engineer or dev: releases to QA machine
  • dev: starts bugfixes from backlog
  • QA: test plans complete, testing  of planned work begins

3/11


bugfixes from backlog completed

  • dev:  start bugfixes for planned work
  • qa: verifies backlog fixes
  • customer relations: sends an early notification to thalia-info

3/18

 

final bugfixes completed

  • dev: all new development occurs in a new branch
  • qa: verifies final bugfixes 

3/??

 

QA gives green light to release

  • qa: all fixes verified, no blockers
  • customer relations: sends an immanent release announcement to thalia-info 24-48 hours before release
  • release engineer: 24 hours before release, notify server ops of service outage

3/24

 

release to production

  • release engineer and ops: release code
  • release engineer: send confirmation to server ops that release was successful
  • customer relations: send confirmation to thalia-info that release was successful

3/25 or 3/26

 

...