High-Level Timeline (standard approach)

(info) September thru the end of October - Plan, create/update test scripts in ALM, move pending support & project work into production.

...

(info) 12/12/2018 - Development Freeze ends

(big grin)

Alternate High-Level Timeline #1

(tick) September thru the end of October - Plan, create/update test scripts in ALM, move pending support & project work into production.

...

(info) 11/21/2018 - Development Freeze ends

(sad)

Alternate High-Level Timeline #2

(tick) September thru the end of October - Plan, create/update test scripts in ALM, move pending support & project work into production.
(tick) 10/11/2018 - SAP release of year end base level support pack
(tick) 11/01/2018 - Development Freeze begins

 

(tick) 10/22/2018 - End of day production snapshot to be used to refresh test environments (9/24 for SF3)
(tick) 11/06/2018 - Unit test
(tick) 11/08/2018 - Last date to implement support & enhancement changes until freeze ends on 12/12/201

(tick) 11/01/2018 - 11/02/2018 Controlled Payroll Runs (SH2)

(info) 11/14/2018 - 11/30/2018 (11 business days) - System Integration Test (regression test fixes: 12/3-4/2018)

(info) 12/07/2018 - Go-live weekend! (start Friday at 5pm)

(info) 12/12/2018 - Development Freeze ends