Project cut-over status of the upgrade, see below,  will be posted on this wiki page beginning at noon on Friday 12/7 through noon on Monday 12/10.  The Project Manager will update this message as needed.  A conference call number (webex) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.

Project Status: 
All preparations tasks for this weekend’s application of SAP’s YE Support Packs to production have been completed. The system has been isolated and SAP is in the process of upgrading PS1, SAP Mobile and GRC as planned. This process will continue through Saturday.

...