End of day production snapshot from 9/30 to be used to refresh test environments

----------

(info) Oct 10 - SAP release of year end base level support pack (SAP)
(info) Oct 10 - Last transport meeting for production support & enhancement changes until support pack work is complete (November 25, 2019)
(info) Oct 10 - Restricted Development Period begins
(info) Oct 17 - Oct 30 - Unit test - IS&T SAP Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP)

...

Oct 31 - Nov 1 -  Controlled Payroll

...

Run Test  - (IS&T HR Support Team)
(info) Oct 31 - Nov 12 - System Integration Test  (Central Office Business Teams)

 

(info) Nov 13 - Nov 15 - Bug fixes and regression testing (Central Office Business Teams and IS&T)

(info) Nov 22 - 24 - Go-live weekend! (start Friday at 5pm)

(info) Nov 25 - Restricted Development Period ends.  PS1 is ready for use