Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

The last regularly scheduled transport release to Production will take place on Thursday, October 10, 2019. Development in SF2 will be allowed through Friday, October 11, 20182019 after which  a restricted window of non-critical transports to SH2 and Production will be in effect until after the Support Pack Project Go Live date. The normal Production transport import schedule will resume on Thursday, November 20, 2019. Migrations to the Test environments (SH1 - PreSP QA) and Production will be limited to critical fixes that need to be moved to Production as soon as possible before the project go-live date. Starting on October 11, a special transport procedure will be enforced for changes to SAP. This section explains the approval process. It lists the necessary approvals and documentation, and what steps you need to take in ZUTTREQ. Questions about this process should be directed to Elda Prudden, Transport Coordinator, at  eprudden@mit.edu or 617-253-5153.

...

Transports generated during Unit Testing will be accumulated and moved as a group as part of the Support Pack application process to the test system, SH2.
Transports generated during SIT will be imported into SH2 twice a day (shortly after 12 noon and then again after 5pm). Requests must be received by 11:30am and 4:30pm, respectively.
These transports must be associated with RT tickets recorded in the Request Tracker SAP::Test Issues queue under project name "SAP Support Packs 20182019".

Transport path = SF2 -> SH2
Approver: Frank Quern

...

Before development is begun, it should be clear the business owner considers the problem is critical and requires an immediate fix. An email message describing the situation must be sent to Frank Quern (fquern@mit.edu), with a copy sent to Eping (Lucia) Wei ( lma@mitElda Prudden (eprudden@,mit.edu), to facilitate consideration of the critical fix. After review Frank will request approval to migrate the fix to Test from one of the business members of the Steering Committee.

...

  • One of the business members of the Steering Committee
  • Frank Quern (PO), Garry Zacheiss Olu Brown (backup)

The functional team must follow the standard QA Issue Resolution procedure, which includes the SAP mini-spec and associated test case documents.

...

All transports must be associated with a Request Tracker (RT) ticket recorded in the Functional Team's Support queue and within the  RT SAP::Test Issue queue under the project name 'SAP Support Packs 20182019'. These transports must be tested twice, once in the production support path (SH1), then in the Support Pack upgrade path (SF2 -> SH2), before the transport(s) can be imported into production.

...

Resumption of normal transport cycle

On December 12November 18, 2018 2019 SAP system SH2 will be opened for normal testing activities to all IS&T SAP support personnel and business owners. The normal QA procedures (documents in the review folders, all business owner approvals captured, RT tickets updated) will resume at that time as well.  All changes approved on or after December 12November 18, 2017 2019 will be considered part of the December 13, 2018 the November 20, 2019 transport cycle.

Transport Coordinator Instructions:

...