Oct 17 - Nov 1: Automated Testing SF3
Oct 17 - Oct 18 - Unit test  SF3 - IS&T

...

and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP)
Oct 21 - Oct 25 - Unit test  SF2 - IS&T

...

and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP)
Oct 28 - Oct 29 -  Controlled Payroll Run Test  - (IS&T HR and EpiUse Support Team)
Oct 28 - Nov 6 - System Integration Test  (Central Office Business Teams)
Nov 7 - Nov 8 - Bug fixes and regression testing (Central Office Business Teams

...

, IS&T and EpiUse)
Nov 11 - Nov 15 - Uptime Production Cutover Activities

...