Oct 17 - Oct 18 - Unit test SF3 - IS&T and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) - complete
Oct 21 - Oct 25 - Unit test SF2 - IS&T and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) -
...
complete
Oct
...
29- Oct
...
30 - Controlled Payroll Run Test - (IS&T HR and EpiUse Support Team)
Oct
...
29 - Nov
...
13- System Integration Test (Central Office Business Teams)
Oct
...
29 - VPF test to compare year-to-date tax information with production
Nov
...
14 - Nov
...
15 - Bug fixes and regression testing (Central Office Business Teams, IS&T and EpiUse)
Nov
...
18 - Nov
...
22 - Uptime Production Cut-over Activities
Nov
...
22 - Nov
...
24 - Go-live weekend! (start Friday at 5pm)
Nov
...
25 - Upgraded PS1 is ready for use
---------