Oct 21 - Oct 25 - Unit test SF2 - IS&T and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) - complete
Oct 29- Oct 30 - Controlled Payroll Run Test - (IS&T HR and EpiUse Support Team) -
...
Complete
Oct 29 - Nov 13- System Integration Test (Central Office Business Teams) - in progress
...