Oct 21 - Oct 25 - Unit test  SF2 - IS&T and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) - complete
Oct 29- Oct 30 -  Controlled Payroll Run Test  - (IS&T HR and EpiUse Support Team) -

...

Complete
Oct 29 - Nov 13- System Integration Test  (Central Office Business Teams) - in progress

...