 Disaster Recovery Test Plan Task List

The As discussed in recent SAP status meetings, IS&T management has indicated that we should proceed with an SAP disaster recovery test on Saturday, December 14 2019 . The understanding is that such a test would will include:

Tests Verification involving failover Failover and subsequent failback Failback of:--

  • ERP system PS1

...

  • GRC system ACP

...

  • NetWeaver/ADS system DSP

...

  • SAP Mobile system SMP with SAP Load Balancer hecsmpweb01.hec.mit.edu

...

  • OpenText (HDB) system OTP

...

  • DataMart systems DMP and DS1

...

  • Cloud Connector system HCC

...

and including the DR site IaaS servers--

  • OTP application server (vhmitotpai01)

...

  • SFTP (vhmitftp02)

...

  • BSP (vhmitbspdb03

...

  • )

...

 Disaster Recovery Test Plan Task List

 

...