Deck of Cards
idIssue
Card
labelSummary

This process can be started by the Administrative Assistant, CC Director, CC Planner, CC Planning Director, CC Planning Manager, Director of Finance and Administration, eB Admin, Furniture Designer, OCP Planner, Program Manager, Project Coordinator, Project Manager, SPT Commissioning Lead, SPT Lead, VPF Strategic Sourcing,

This process is also started when Send and Initialize is used as the notification option in the 4.0 Bidding Step

Card
labelProcess Map

Card
labelStep Descriptions

Note that these step descriptions are in the process of being updated.

Toggle Cloak
Start

Cloak
  • The Project Coordinator or Project Manager fills out the required fields and executes the Submit action.
  • The next step is PM Initiate Process?

When asked to identify the type of contract being requested this document may be helpful.

Toggle Cloak
Total $ <= 0?

Cloak
  • The Total $ <=0? conditional checks if the amount for all commitment items entered is less than or equal to $ 0.
  • If True (Yes) the next step is Initiator Revise.
  • If False (No) the next step is PjFnAmt < ComAmt?

Toggle Cloak
PjFnAmt < ComAmt?

Cloak
  • The PjFnAmt < ComAmt? conditional checks if the Projected Final Contract Amount is less than the amount of the Commitment you are trying to establish.
  • If True (Yes) the next step is Initiator Revise.
  • If False (No) the next step is PjFnAmt < ComAmt?

Toggle Cloak
Initiator Revise

Cloak
  • The Initiator Revise step shares a page layout with the Start step and allows the Process Initiator to make changes and resubmit the process.
  • When the Initiator takes the Resubmit action the next step is the conditional question PM Initiate Process?

Toggle Cloak
PM Initiate Process?

Cloak
  • The PM Initiate Process? conditional step determines the path the process will take based on if the data field “Did the PM Initiate the Process?has been marked “Yes” or "No" in the previous step.
  • If True (Yes) the next step is Contract Required?
  • If False (No) the next step is PM Review

Toggle Cloak
Contract Required?

Cloak
  • The Contract Required? conditional step determines the path the process will take based on if the data field “Contract Required?” has been marked “Yes” or "No" in the previous step.
    • NOTE: Contract is NOT Required if PO is for Material or Equipment ONLY purchase,  Environmental Agreement < $5k, Consulting Agreement < $10k, or Construction Contract < $25k.
  • If True (Yes) the next step is Contract > $10K?
  • If False (No) the next step is Purch Req M.M.

Toggle Cloak
Contract >$10K?

Cloak
  • The Contract >$10K? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
  • If True (>$10K) the next step is Vendor Manager Review of SoS.
  • If False (<=$10K) the next step is Purch Req M.M.

Toggle Cloak
PM Review

Cloak
  • The PM reviews the process and verifies the Contract or PO being added to the project and chooses the Submit action.
  • The next step is Contract Required?

Toggle Cloak
Vendor Manager Review of SoS

Cloak
  • The Vendor Manager reviews the Selection of Source information and confirms the vendor exists in SAP.
  • If Submit is chosen the next step is Contract Admin Assembles Contract.
  • If Revise is chosen the next step is Initiator Revise 1.

Toggle Cloak
Contract Admin Assembles Contract

Cloak
  • The Contract Admin reviews the process and uploads the assembled Contract Document to be executed.
  • As part of this step the Contract Admin associates a bid process to this PO/Contract process by using the Contract Number Lookup. (Instructions are in included on the process page)
  • If Submit is chosen the next step is Initiator Reviews Contract.
  • If Revise is chosen the next step is Initiator Revise 1.

Toggle Cloak
Initiator Reviews Contract

Cloak
  • The Process Initiator reviews the Contract Document.
  • If Submit is chosen the next step is CA Manager Reviews.
  • If Revise is chosen the next step is Contract Admin Assembles Contract.

Toggle Cloak
CA Manager Reviews

Cloak
  • The DoF Procurement Manager and the Contract Admin Manager reviews the Contract Document and determine whether or not it meets the requirements for OGC Counsel Review.
  • If Submit is chosen the next step is Contract Admin Releases Contract.
  • If Revise is chosen the next step is Initiator Revise 1.
  • If To DOF Counsel is chosen the next step is OGC Counsel Review.

Toggle Cloak
OGC Counsel Review

Cloak
  • The DOF General Counsel reviews the Contract Document.
  • If Submit is chosen the next step is Contract Admin Releases Contract.
  • If Revise is chosen the next step is Initiator Revise 1.

Toggle Cloak
Contract Admin Releases Contract

Cloak
  • The Contract Admin sends the contract to the vendor for review and signature, and records the date the contract was sent.
  • If Submit is chosen the Contract Document has been sent to the vendor. The next step is Vendor Executes Contract.
  • If Revise is chosen the next step is Contact Admin Assembles Contract.

Toggle Cloak
Initiator Revise 1

Cloak
  • The Initiator Revise 1 step allows the Process Initiator to make changes and resubmit the process.
  • When the Initiator takes the Resubmit action the next step is Vendor Manager review of SoS.

Toggle Cloak
Hold for Vendor Contract Execution

Cloak
  • The Contract Admin reviews the signed contract received from the vendor, records the date they received the signed contract and then removes and replaces the unsigned contract with the received vendor signed contract into the Contract Document field.
  • If Submit is chosen the next step is Contract Admin Final Review.
  • If Revise is chosen the next step is Contract Admin Releases Contract.

Toggle Cloak
Contract Admin Final Review

Cloak
  • The Contract Admin Manager reviews the vendor signed contract for final review before going to directors steps.
  • If Submit is chosen the next step is Campus Construction?
  • If Revise is chosen the next step is Hold for Vendor Contract Execution.

Toggle Cloak
Campus Construction?

Cloak
  • The Campus Construction? conditional determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is Academic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal.
  • If True (Yes) the next step is SP&T Program?
  • If False (No) the next step is OCP?

Toggle Cloak
SPT Program?

Cloak
  • The SPT Program? conditional determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is System Performance & Turn-over.
  • If True (Yes) the next step is SPT Director Review
  • If False (No) the next step is Proj. Contract>$10m?

Toggle Cloak
SPT Director Review

Cloak
  • The SPT Director reviews the Contract Document attached to the process.
  • If Submit is chosen the next step is Proj. Contract>$10m?
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
Proj. Contract>$10m?

Cloak
  • The Proj. Contract>$10m? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
  • If True (>$10m) the next step is Vendor Manager Review of SoS.
  • If False (<=$10m) the next step is Purch Req M.M.

Toggle Cloak
CC Director Review

Cloak
  • The CC Director reviews the Contract Document attached to the process and if required attaches the CC Director Memo.
  • If Submit is chosen the next step is CA Mgr & Dir. Finance.
  • If Revise is chosen the next step is Initiator Revise 3.
  • If Send To OGC is chosen the next step is OGC Counsel Review.

Toggle Cloak
CC Director Executes Contract

Cloak
  • By taking the Submit action at this step the CC Director is Executing the contract.
  • If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
CA Mgr & Dir. Finance

Cloak
  • The Contract Admin Manager and the Director of Finance and Administration review the attached CC Director Memo and upload the Executed Memo to the process.
  • If Submit is chosen the next step is VP, CSS Reviews
  • If Revise is chosen the next step is CC Director Review

Toggle Cloak
OCP?

Cloak
  • The OCP? conditional determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is OCP.
  • If True (Yes) the next step is Proj. Contract> $500k?
  • If False (No) the next step is CSM?

Toggle Cloak
Proj. Contract> $500k?

Cloak
  • The Proj. Contract> $500k? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
  • If True (>$500K) the next step is CSM Director Executes
  • If False (<=$500K) the next step is CSM Director Reviews

Toggle Cloak
OCP Director Review

Cloak
  • The OCP Director reviews the Contract Document attached to the process.
  • If Submit is chosen the next step is Prj Contract > $10mil?
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
OCP Director Execute

Cloak
  • By taking the Submit action at this step the OCP Director is Executing the contract.
  • If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
CSM?

Cloak
  • The CSM? step determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is CSG or R&M.
  • If True (Yes) the next step is Proj. Contract>$5m?
  • If False (No) the next step is Utilities Program?

Toggle Cloak
Proj. Contract>$5m?

Cloak
  • The Proj. Contract>$5m? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
  • If True (>$5m) the next step is CSM Director Review.
  • If False (<=$5m) the next step is CSM Director Executes.

Toggle Cloak
CSM Director Executes

Cloak
  • By taking the Submit action at this step the O&M Director is Executing the contract.
  • If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
CSM Director Review

Cloak
  • The SPT Director reviews the Contract Document attached to the process.
  • If Submit is chosen the next step is Prj Contract > 10mil?
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
Utilities Program?

Cloak
  • The Utilities Program? step determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is CUP - OPS, or Utilities.
  • If True (Yes) the next step is Contract> $1M.
  • If False (No) the next step is FEG Program?

Toggle Cloak
Contract> $1M

Cloak
  • The Proj. Contract>$10m? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
  • If True (>$1m) the next step is Utilities Director Review.
  • If False (<=$1m) the next step is Utilities Director Executes.

Toggle Cloak
Utilities Director Execute

Cloak
  • By taking the Submit action at this step the Utilities Director is Executing the contract.
  • If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
Utilities Director Review

Cloak
  • The SPT Director reviews the Contract Document attached to the process.
  • If Submit is chosen the next step is Proj. Contract>$10mil?
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
FEG Program?

Cloak
  • The FEG Program? step determines the path the process will take based on the Program Type of the Project Details page. This conditional will evaluate as True if the Program Type is Energy, or SEG.
  • If True (Yes) the next step is FEG Director Review.
  • If False (No) the next step is VP, CSS Executes.

Toggle Cloak
FEG Director Review

Cloak
  • The FEG Director reviews the Contract Document attached to the process.
  • If Submit is chosen the next step is Proj. Contract>$10mil?
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
Prj Contract > 10mil?

Cloak
  • The Prj. Contract > 10mil? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount
  • If True (>$10m) the next step is VP, CSS Reviews.
  • If False (<=$10m) the next step is VP, CSS Executes.

Toggle Cloak
VP, CSS Reviews

Cloak
  • The VP for Campus Services and Stewardship reviews the Contract Document attached to the process.
  • If Submit is chosen the next step is Campus Construction>$10mil <$100mil?
  • If Revise is chosen the next step is Initiator Revise 3CA Mgr & Dir. Finance.

Toggle Cloak
CPVP, CSS Executes

Cloak
  • By taking the Submit action at this step the CC Director is Executing VP for Campus Services and Stewardship is executing the contract.
  • If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
>$10mil <$100mil?

Cloak
  • The Proj. Contract>$10m>$10mil <$100mil? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
  • If True (>$10m and <$100mil) the next step is Vendor Manager Review of SoSVP Finance Executes.
  • If False (<>=$10m$100mil) the next step isPurch Req M.M EVPT Executes.

Toggle Cloak
VP Finance Executes

Cloak
  • By taking the Submit action at this step the CC Director is Executing VP for Finance is executing the contract.
  • If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
EVPT Executes

Cloak
  • By taking the Submit action at this step the CC Director EVP&T Office is Executing the contract.
  • If Submit is chosen the next step is Contract Signature followed by the SAP PO Hold Step.
  • If Revise is chosen the next step is Initiator Revise 3.

Toggle Cloak
Initiator Revise 3

Cloak
  • The Initiator Revise 3step allows the Process Initiator to make changes and resubmit the process.
  • When the Initiator takes the Resubmit action the next step is Contract Required?
  • The Contract <$10m conditional step determines the path the process takes based on the Current Commitment value being greater than or less than $10m.
  • If True (Yes) the next step is IBO Director Executes Contract.
  • If False (No) the next step is IBO Director Reviews Contract.

Toggle Cloak
Contract Signature

Cloak
  • Contract Signature will finalize the director's electronic signatures using DocuSign. Once complete it will automatically take the Code Complete action. (Signifies that e-Builder has completed a task}
  • The next step is SAP PO Hold Step
  • The IBO Director reviews the process and executes the contract, then takes the Submit action.
  • The next step is Contract Signature.

Toggle Cloak
Purch Req M.M.

Cloak
  • The IBO Director reviews the process and the contract, then takes the Submit actionThe Purch Req M.M. step is a mail merge automation step that completes the purchase requisition from the purchase requisition template.
  • The next step is Contract <100mis CRSP Admin & Procurement Review.

Toggle Cloak
CRSP Admin & Procurement Review

Cloak
  • The Contract <$100m conditional step determines the path the process takes based on the Current Commitment Value being greater than or less than $100m.
  • If True (Yes) the next step is Deputy EVP Executes Contract.
  • DoF Procurement Manager and the Contract Admin Manager review the process and confirms that the vendor exists in SAP and an SAP issued vendor number is correctly entered in the "Company Number" field in the Contacts Module.
  • If Submit is chosen the next step is >$25K?
  • If Revise is chosen the next step is Initiator Revise 2If False (No) the next step is Deputy EVPT Review.

Toggle Cloak
>$25K?

Cloak
  • The Deputy EVPT reviews the process, signs the contract and takes the Submit action. Proj. Contract>$10m? conditional step determines the path the process will take based on the amount entered for the data field Projected Final Contract Amount.
  • If True (>$1m) the next step is Utilities Director Review.
  • If False (<=$1m) the next step is Utilities Director ExecutesThe next step is Contract Signature.

Toggle Cloak
Initiator Revise 2

Cloak
  • The Deputy EVPT reviews the process and the contract and takes the Submit action.
  • The next step is Contract Signature.

Toggle Cloak
SAP PO Hold Step

Cloak
  • The EVPT Office reviews the process and the contract and takes the Submit action.
  • The next step is Contract Signature.

Toggle Cloak
PO M.M

Cloak
  • Contract Signature will finalize the director's electronic signatures using DocuSign. Once complete it will automatically take the Code Complete action. (Signifies that e-Builder has completed a task}
  • The next step is SAP PO/Contract Hold Step.

Toggle Cloak
AA sends Exec. PO\Contract to vendor

Cloak
  • The Purchase req MM step is a mail merge automation that completes the purchase requisition from the purchase requisition template.
  • The next step is DoF Procurement Review.

Toggle Cloak
Finish

Cloak

 

 

Card
labelCommitment Line Intructions

Enter information for each commitment item.

  • Item Number - a sequential number denoting each line.
  • Budget Line Item - Associate each entry with a Budget Line Item.
  • Current Budget - Displays the current budget.
  • Description - editable field for a description.
  • Retainage Percent - enter the retainage percent when applicable.
  • Amount - the amount of the the commitment line
  • Allowance Item - Check if it is an allowance item.
  • Custom Fields - used to enter the cost object.

Pay particulate attention to the Retainage percentage as that determines how retainage is calculated when invoices are submitted.

A Retainage of five percent should be expressed as 5.00 (as in the example)

The following list of items, though part of the budget template, cannot be used to generate a commitment. You cannot place internal charges on a PO.

If you are issuing a PO to cover vendor expenses use the reimbursable line item for that vendor type. For example, for A/E expenses use B-30-125 A/E Reimbursables.

Do Not Use list is below:

A15-005

A15-005  DoF Project Administration

A15-010

A15-010  OCP Project Administration

A15-015

A15-015  Utilities Project Administration

A15-020

A15-020  SEG Project Administration

A15-025

A15-025  EHS Project Administration

A15-035

A15-035  Service and Support-Staff

A15-045

A15-045  Employee Benefit Charges (EB) - General

A20-050

A20-050  Travel Expenses

C50-685

C50-685  Other MIT Internal Charges

C55-730

C55-730  Steam

C55-745

C55-745  Chilled Water

F95-835

F95-835  EVPT Contingency

F96-840

F96-840  DoF Contingency

 

 

Card
labelOutput - The Purchase Order Document

This process will print a Purchase Order document that can be sent to the vendor.

Purchase Order

This process is used for both signed contracts and purchase orders and it will display the desired document in the AA Sends Exec. PO/Contract to Vendor ... step.

When a contract is displayed the supporting purchase order is still generated. To print the purchase order:

  1. Click the Print button.
  2. Click the Merge Templates radio button.
  3. Choose Purchase Order from the drop down menu.
  4. Click the Print Button on the Mail Merge Templates menu.

Sample Purchase Order Document

PO Mail Merge FieldNotes/Description
Purchase Order NumberThe Purchase Order Number in the top right hand corner of the PO (highlighted in yellow on this example) will only appear when the process has progressed through the SAP PO/Contract Hold step. Prior to that step it is possible to preview the Purchase Order, but the PO number will not appear on the form.
DateThe date field is the date that the purchase order mail merge is generated. If you reprint the purchase order the date will update.
Vendor and Vendor AddressThe Vendor and vendor addresss information is derived from the Contacts module in e-Builder. If address information is missing from that module the PO fields for this information will be blank. If you update the Contacts information in e-Builder you may reprint the PO and the information will appear as updated.
Ship ToThis information is derived from the building information that is part of the e-Builder project information. If room information has been added to e-Builder the room information will also print on the purchase order.
Delivery DateThis information is hardcoded. Each purchase order will have "Per Previous Agreement" in this field. Changing this field requires the assistance of an e-B admin.
Shipping MethodThis information is hardcoded. Each purchase order will have "N/A" in this field. Changing this field requires the assistance of an e-B admin.
Shipping TermsThis information is hardcoded. Each purchase order will have "N/A" in this field. Changing this field requires the assistance of an e-B admin.
Payment TermsThis information is hardcoded. Each purchase order will have "Net 30" in this field. Changing this field requires the assistance of an e-B admin.
ItemsEach commitment line will use the dollar figure and commitment description for the corresponding commitment in e-Builder. Each line will be sequentially numbered beginning with 001.
Project NumberThe project number from e-Builder.
Project NameThe project name from e-Builder. The project name may contain the room number.
Project ContactThe proect contact is derived from Project Manager 1 in e-Builder. The phone number is hard coded and is the general switchboard number for MIT DoF.
Description of Services 
MIT Contract # 
Vendor Billing Instruction 
MIT Sales and Use Tax Exemption