labelSummary

This process can be started by the A/E Lead, Administrative Assistant, CC Planner, Consultant, Contractor, OCP Planner, Project Manager and SPT Lead.

This process is used to submit, review and approve the following: Amendments to Commitments (Contracts) & Purchase Orders issues to Professional Services vendors (A/E, Designers, Consultants), Master Design Agreement Release Change Orders, and Phased Purchase Order Releases (under and executed design contract).

Card
labelProcess Map

Card
labelStep Descriptions

Toggle Cloak
Start

Cloak
  • The Process Initiator fills out the required fields and chooses to submit.
  • The next step is MDA Release?

Toggle Cloak
MDA Release?

Cloak
  • The MDA Release? Conditionalchecks if Master Design Agreement (MDA) Change Order was selected for the Type of Change field.
  • If True (Yes) the next step is PM Enters Release
  • If False (No) the next step is PO Release?

Toggle Cloak
PO Release?

Cloak
  • The PO Release? Conditional checks if Master Design Agreement (MDA) Change Order was selected for the Type of Change field.
  • If True (Yes) the next step is PO CO MM
  • If False (No) the next step is A/E Initiated?

Toggle Cloak
A/E Initiated?

Cloak
  • The A/E Initiated? Conditional checks if the role of the Process Initiator was A/E Lead or Consultant.
  • If True (Yes) the next step is PSA Mail Merge
  • If False (No) the next step is PSA MM (for A/E man

Toggle Cloak
PM Enters Release

Cloak
  • The Project Manager adds the appropriate release from the 05.02.05 MDA Release(s) folder of project 11112, and fills out any required fields.
  • If Submit is chosen the next step is Program Manager Review MDA
  • If Revise is chosen the next step is Initiator Revise MDA
  • If Void is chosen the next step is Finish and the process is set to a Void status.

 

Toggle Cloak
Program Manager Review MDA

Cloak
  • The Program Manager reviews the Master Design Agreement Release details
  • If Submit is chosen the next step is Vendor Signature
  • If Revise is chosen the next step is Initiator Revise MDA

Toggle Cloak
Contracts Group

Cloak
  • The Contract Admin reviews the Master Design Agreement Release details, makes any changes and if necessary re-uploads the document in the PSA/MDA for Signature field.
  • If Submit is chosen the next step is Program Manager Review MDA
  • If Revise is chosen the next step is Initiator Revise MDA
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
Initiator Revise MDA

Cloak
  • The Initiator Revise MDA step allows the Process Initiator to make changes and resubmit the process.
  • If Resubmit is chosen the next step is MDA Release
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
 Vendor Signature

Cloak
  • The Consultant, A/E Lead and/or the Project Manager takes the appropriate action to sign the document.
  • If Submit is chosen the next step is Program Manager Review MDA
  • If Revise is chosen the next step is Initiator Revise MDA

Toggle Cloak
PO CO MM

Cloak
  • The PO CO MM step is a mail merge automation step that completes the Phased Purchase Order Release mail merge document.
  • The next step is PM Attaches Contract

Toggle Cloak
PM Attaches Contract

Cloak
  • The Project Manager attaches a copy of the vendor executed contract, and fills out the PM Description of Change (Internal Only) field if necessary.
  • The next step is Program Manager Reviews PO

Toggle Cloak
Program Manager Reviews PO

Cloak
  • The Program Manager reviews the Phased Purchase Order Release details.
  • If Reviewed is chosen the next step is OCP?
  • If Revise is chosen the next step is Initiator Revise PO Release

Toggle Cloak
OCP?

Cloak
  • The OCP? Conditional checks if the Program Type of the project is OCP
  • If True (Yes) the next step is OCP Director Approval
  • If False (No) the next step is CC Director Approval

Toggle Cloak
CC Director Approval

Cloak
  • The CC Director takes the appropriate action to approve the document.
  • If Submit is chosen the next step is SAP Hold Step
  • If Revise is chosen the next step is Initiator Revise PO Release

Toggle Cloak
OCP Director Approval

Cloak
  • The OCP Director takes the appropriate action to approve the document.
  • If Submit is chosen the next step is SAP Hold Step
  • If Revise is chosen the next step is Initiator Revise PO Release

Toggle Cloak
Initiator Revise PO Release

Cloak
  • The Initiator Revise PO Release step allows the Process Initiator to make changes and resubmit the process.
  • If Resubmit is chosen the next step is MDA Release
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
PSA Mail Merge

Cloak
  • The PSA Mail Merge step is a mail merge automation step that completes the Standard PSA mail merge document.
  • The next step is Project Manager Review

Toggle Cloak
PSA MM (for A/E man

Cloak
  • The PSA MM (for A/E man step is a mail merge automation step that completes the Standard PSA mail merge document to be sent to the A/E Lead or Consultant for a manual signature.
  • The next step is PM Attaches Contract

Toggle Cloak
Project Manager Review

Cloak
  • The Project Manager reviews the PSA Details and fills out all required fields.
  • If Submit is chosen the next step is Contracts Group Review PSA
  • If Revise is chosen the next step is Initiator Revise PSA

Toggle Cloak
Contracts Group Review PSA

Cloak
  • The Contract Admin and Contract Admin Manager review the PSA Details and determine whether or not it meets the requirements for OGC Counsel Review.
  • If Reviewed is chosen the next step is Vendor Signs
  • If Send to OGC is chosen the next step is OGC Counsel Review
  • If Revise is chosen the next step is Initiator Revise PSA

Toggle Cloak
OGC Counsel Review

Cloak
  • The DOF General Counsel reviews the PSA Details.
  • If Reviewed is chosen the next step is Vendor Signs
  • If Revise is chosen the next step is Contracts Group Review PSA

Toggle Cloak
Vendor Signs

Cloak
  • The Process Initiator takes the appropriate action to sign the document.
  • If Submit is chosen the next step is Additional Funding?
  • If Revise is chosen the next step is Initiator Revise PSA

Toggle Cloak
PM Review PSA - Manual Req

Cloak
  • The Project Manager fills out all required fields and sends the PSA Document to the Vendor for a manual signature.
  • If Submit is chosen the next step is Hold for Signed PSA
  • If Revise is chosen the next step is Initiator Revise PSA
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
Hold for Signed PSA

Cloak
  • The Project Manager and Contract Admin until they receive back the vendor manually signed PSA document and upload it to the process.
  • The next step is Additional Funding?

Toggle Cloak
Additional Funding?

Cloak
  • The Additional Funding? Conditional checks if Yes was selected for the Additional Project Funding? field.
  • If True (Yes) the next step is Spawn Budget Change (03.03)
  • If False (No) the next step is Program Manager Review

Toggle Cloak
Spawn Budget Change (03.03)

Cloak
  • This step spawns a 03.03 - Contingency Request / True-Up Form / Additional Funding Request (BCHNG) process.
  • The next step is CRSP Admin Mgr. Hold

Toggle Cloak
CRSP Admin Mgr. Hold

Cloak
  • The CRSP Admin holds the process in this step until additional funding has been applied to the project in both e-Builder and SAP.
  • The next step is Program Manager Review

Toggle Cloak
Program Manager Review

Cloak
  • The Program Manager reviews the vendor signed document in the PSA/MDA for Signature field.
  • If Submit is chosen the next step is Campus Construction?
  • If Revise is chosen the next step is Initiator Revise PSA

Toggle Cloak
Initiator Revise PSA

Cloak
  • The Initiator Revise PSA step allows the Process Initiator to make changes and resubmit the process.
  • If Resubmit is chosen the next step is MDA Release
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
Campus Construction?

Cloak
  • The Campus Construction? Conditional checks if the Program Type of the project is Academic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal
  • If True (Yes) the next step is SP&T Program?
  • If False (No) the next step is OCP?

Toggle Cloak
OCP?

Cloak
  • The OCP? Conditional checks if the Program Type of the project is OCP
  • If True (Yes) the next step is EstFinCon> $500K
  • If False (No) the next step is CSM?

Toggle Cloak
CSM?

Cloak
  • The CSM? Conditional checks if the Program Type of the project is CSG or R&M
  • If True (Yes) the next step is EstFinCon> $5m?
  • If False (No) the next step is Utilities Program?

Toggle Cloak
Utilities Program?

Cloak
  • The Utilities Program? Conditional checks if the Program Type of the project is CUP - OPS or Utilities
  • If True (Yes) the next step is Est Fin Cont>$1M
  • If False (No) the next step is FEG Program

Toggle Cloak
FEG Program?

Cloak
  • The FEG Program? Conditional checks if the Program Type of the project is Energy or SEG
  • If True (Yes) the next step is FEG Director Review
  • If False (No) the next step is EstFinCon >$1M

Toggle Cloak
EstFinCon > $1M

Cloak
  • The EstFinCon > $1M Conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is EstFinCon>$10M
  • If False (No) the next step is Dir. Finance Execute

Toggle Cloak
SP&T Program?

Cloak
  • The SP&T Program? Conditional checks if the Program Type of the project is System Performance & Turn-over
  • If True (Yes) the next step is SPT Director Review
  • If False (No) the next step is EstFinCon >$10m

Toggle Cloak
EstFinCon> $500K

Cloak
  • The EstFinCon> $500K Conditional checks if >$500,000<=$1,000,000, >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is OCP Director Review
  • If False (No) the next step is OCP Director Execute

Toggle Cloak
EstFinCon>$5m?

Cloak
  • The EstFinCon>$5m? Conditional checks if >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is CSM Director Review
  • If False (No) the next step is CSM Director Execute

Toggle Cloak
Est Fin cont> $1M

Cloak
  • The Est Fin cont> $1M Conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is Utilities Director Review
  • If False (No) the next step is Utilities Director Execute

Toggle Cloak
SPT Director Review

Cloak
  • The SPT Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>$10M
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
OCP Director Review

Cloak
  • The OCP Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>$10M
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
CSM Director Review

Cloak
  • The M&U Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>$10M
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
FEG Director Review

Cloak
  • The SEG Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>$10M
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
Utilities Director Review

Cloak
  • The Utilities Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>$10M
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
Dir. Finance Execute

Cloak
  • By taking the Approved action at this step the Director of Finance and Administration is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
EstFinCon>$10m

Cloak
  • The EstFinCon>$10m Conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is CC Director Review
  • If False (No) the next step is CC Director Execute

Toggle Cloak
CC Director Review

Cloak
  • The CC Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>10<=100mil
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
CC Director Execute

Cloak
  • By taking the Approved action at this step the CC Director is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
OCP Director Execute

Cloak
  • By taking the Approved action at this step the OCP Director is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
CSM Director Execute

Cloak
  • By taking the Approved action at this step the M&U Director is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
Utilitites Director Execute

Cloak
  • By taking the Approved action at this step the Utilities Director is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
EstFinCon>$10M

Cloak
  • The EstFinCon>$10M Conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is VP, CSS Review
  • If False (No) the next step is VP, CSS Execute

Toggle Cloak
VP, CSS Review

Cloak
  • The VP for Campus Services and Stewardship reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>10<=100mil
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
VP, CSS Execute

Cloak
  • By taking the Approved action at this step the Deputy EVP is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
EstFinCon>10<=100mil

Cloak
  • The EstFinCon>10<=100mil Conditional checks if >$10,000,000<=$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is VP Finance Execute
  • If False (No) the next step is EVPT Execute

Toggle Cloak
VP Finance Execute

Cloak
  • By taking the Approved action at this step the VP for Finance is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
EVPT Execute

Cloak
  • By taking the Approved action at this step the EVP&T Office is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
Initiator Revise 2

Cloak
  • The Initiator Revise 2 step allows the Process Initiator to make changes and resubmit the process.
  • If Resubmit is chosen the next step is MDA Release
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
Amendment Signature

Cloak
  • The Amendment Signature step is a e-Signature File Download automation step that completes the Docusign envelope.

  • The next step is SAP Hold Step

Toggle Cloak
SAP Hold Step

Cloak
  • Hold step for SAP Processing.
  • Once processed the next step is the PO MM step.

Toggle Cloak
PO MM

Cloak
  • The PO MM step is a mail merge automation step that completes the PSA PO CO MM mail merge document.
  • The next step is Project Manager Review

Toggle Cloak
AA/Contracts Sends Exec-PSA to Vendor

Cloak
  • The Administrative Assistant and Contract Admin should review the documents attached to the process, send the executed documents to the vendor and record the date that the executed documents were sent.
  • The next step is Finish.

Toggle Cloak
Finish

Cloak