...
Include any associated Request Tracker (RT) ticket numbers from the RT SAP::Test Issues queue (under the project name 'SAP Support Packs 2020), if they exist, in the ZUTTREQ 'Purpose' block. NoteNote: Any in-process changes saved during step 1 will need to be manually merged into the corrected objects after the development freeze.
...
Transports generated during Unit Testing will be accumulated and moved as a group as part of the Support Pack application process to the test system, SH2.
Transports generated during SIT will be imported into SH2. These transports might be associated with RT tickets recorded in the Request Tracker SAP::Test Issues queue under project name "SAP Support Packs 2020".
Transport path = SF2 -> SH2
Approver: Lori Singer
...
Transports might be associated with a Request Tracker (RT) ticket recorded in the Functional Team's Support queue and within the RT SAP::Test Issue queue under the project name 'SAP Support Packs 2020'. These transports must be tested twice, once in the production support path (SH1), then in the Support Pack upgrade path (SF2 -> SH2), before the transport(s) can be imported into production.
...