...
Project cut-over status of the upgrade, see below, will be posted on this wiki page beginning at noon on Friday 12/4/2020 through noon on Monday 12/7/2020. The Project Manager will update this message as needed. A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.
| Friday Saturday December 4 8PM5 9AM: Production SAP is unavailable. SAP Upgrade is in progress.HEC upgrade tasks are complete. MIT Technical tasks and validations have started |
|---|
...