The transport tracking goal is to move as much pending work to production as soon as possible, before the 5:00 pm 10/21/2021 production restricted window (the instructions for how to derive the details for the table below can be found by following the Transport Coordinator Instructions & Audit Process link on previous page in project Wiki).
| Transport status | # of Transports as of 10/01/21 | # of Transports as of 10/ | ??/2115/21 (as of ~10:30AM) | # of Transports as of 10/15/21 (pre-SF2 Recovery, as of ~4:30PM) | # of Transports as of 10/ | ??18/21 (pre-2nd SF2 Recovery, as of ~6pm) | # of Transports as of 10/18/21 | Comments |
| SF2 transports not released | 45 | 37 | 21 |
| ||||
| SF2 Released not in SH2 | 149 | 110 | 145 | |||||
| SF2 Released in SH2 not in PS1 | 130 | 108 | 108 | |||||
| SF3 Mods in SF2 not in SH2 | 9 | 7 | 7 | |||||
| SF3 Mods in SF2 SH2 not in PS1 | 0 | 2 | 2 |
See attached spreadsheets below for details.
...