Deck of Cards
idCRSPSC
Card
labelSummary
Card
labelProcess Map

 

Card
labelStep Descriptions

Toggle Cloak
Process Start 

Cloak
  • This process can be started by the CRSP Admin, CRSP Admin Assistant or the e-B Admin.
  • The initiator fills out the required fields then clicks Submit.  Drafts of the process are visible to CRSP Admin and the CRSP Admin Assistant.
  • The next step is CRSP Assistant Update Details

Toggle Cloak
CRSP Assistant Update Details

Cloak
  • The CRSP Admin Assistant reviews the process, completes the required fields and clicks Submit.
  • The next step is CRSP Screening Review

Toggle Cloak
CRSP Screening Review

Cloak

CRSP Admin or CRSP Admin Assistant reviews the process, completes the required fields and takes one of the following actions:

  • If the Revise action is taken theNext Step is CRSO Assistant Update Details.
  • If the Denied action is taken the Next Step is Finish.
  • If the Proceed to Provost action is taken the Next Step is Provost Office Review
  • If the Team Assignment action is taken the next step is Assign a Project Manager.
    • When Team Assignment is selected the process is sent for action by the e-B admin. A submit from the eB admin spawns the Team Assignments process.
  • If the Planner Only action is taken the next step is OCP Assignor.
  • If the Put On - Hold action is taken the next step is Hold Step.
  • If the Misc Projects action is taken the next step is eB Admin.
  • If the Prgm/Manager Change action is taken the next step is eBAdmin.

Toggle Cloak
Hold Step

Cloak
  • A process remains in this step until taken off hold At that point, the Hold for eB Admin User reviews the process and takes one of the following actions:

Void

Next Step:
  • If the Void action is taken the next Step is Finish Step.
  • If the Return to Screening
Next Step:
  • action is taken the next Step is CRSP Screening Review.

Toggle Cloak
Provost Office Review

Cloak
  • The actor selected from the CRSP Screening Review step reviews the process, adds comments, and takes one of the following actions:
  • If the Revise to CRSP Screening
Next Step:
  • action is taken the next step is CRSP Screening Review.

Toggle Cloak
OCP Assignor

Cloak
  • The OCP Assignor reviews the process, fills out the required field and takes one of the following actions:
  • If the Update Project
Next Step:
  • action is taken the next step is eB Admin.
  • If the Ask CRSP Admin
Next Step:
  • action is taken the next step is CRSP Screening Review.

 

Toggle Cloak
9eB eB Admin

Cloak
  • The eB Admin reviews the process, creates the project, updates the required fields and takes one of the following actions:
  • If the Submit to MOU
Next Step:
  • action is taken the next step is MOU Required?
  • If the Submit to Finish
Next Step: Finish Step
  • action is taken the next step is Finish.

Toggle Cloak
MOU Required?

Cloak
  • The MOU Required conditional step determines the path the process takes based on the value found in the MOU Required field as marked in a previous step. One of the following paths is taken:
  • If the conditional evaluates to True (Yes)
Next Step:
  • the next step is PM Verifies Team Assignment.
  • If the conditional evaluates to False (No)
Next Step: Finish Step
  • the next step is Finish.

Toggle Cloak
eBAdmin

Cloak
  • The eB Admin reviews the process and makes the indicated change to the Program Manager. They then take the following action:
  • When the Submit action is taken, the next step is Assign a Project Manager.

Toggle Cloak
PM Verifies Team Assignment

Cloak
  • The Project Manager verifies that the Team Assignments have been completed, confirms in the process, and takes the following action:

Submit

Next Step:
  • When the Submit action is taken the next step is MOU and Stage 1 Budget (Spawn).

Toggle Cloak
Team Assignments (Spawn)

Cloak
  • When the Submit action is taken from the PM Verifies Team Assignment step, the process proceeds to this spawn step which starts the 02
/
  • .02 - MOU and Stage 1 Budget - CRSP (non-cost) process.
Next Step: Finish Step
  • When the Submit action is taken the next step is Finish.

Toggle Cloak
Finish

Cloak