Result or Product of this Process

Round Rectangle
bgcolor#e6f2ff

The 06.03 - PSA, MDA or PO Release (PSA) process is used for the following:

  • Master Design Agreement (MDA) Release
  • Professional Services Amendment (Contract & Purchase Order Agreement)
  • Purchase Order Release by Phase (no change to contract)
Deck of Cards
idPSA
Card
labelSummary

This process can be started by the A/E Lead, Administrative Assistant, CC Planner, Consultant, Contractor, OCP Planner, Project Manager and SPT Lead.

This process is used to submit, review and approve the following: Amendments to Commitments (Contracts) & Purchase Orders issues to Professional Services vendors (A/E, Designers, Consultants), Master Design Agreement Release Change Orders, and Phased Purchase Order Releases (under and executed design contract).

Card
labelProcess Map
 
Card
labelStep Descriptions

Toggle Cloak
Start

Cloak
  • The Process Initiator fills out the required fields and chooses to submit.
  • The next step is MDA Release?

Toggle Cloak
Project Status Check

Cloak
  • The Project Status Check Conditionalchecks if the Project Status is not an Active one.
  • If True (Yes) the next step is Project Status is Incorrect
  • If False (No) the next step is MDA Release?

Toggle Cloak
Project Status is Incorrect

Cloak
  • The Initiator holds the project in this step until the project status is updated to an Active one via a . Once the status is updated the I've run a PMUa action should be taken.
  • If the I've run a PMUa action is taken the next step is Project Status Check.

Toggle Cloak
MDA Release?

Cloak
  • The MDA Release? Conditionalchecks if Master Design Agreement (MDA) Change Order was selected for the Type of Change field.
  • If True (Yes) the next step is PM Enters Release
  • If False (No) the next step is PO Release?

Toggle Cloak
PO Release?

Cloak
  • The PO Release? Conditional checks if Master Design Agreement (MDA) Change Order was selected for the Type of Change field.
  • If True (Yes) the next step is PO CO MM
  • If False (No) the next step is A/E Initiated?

Toggle Cloak
A/E Initiated?

Cloak
  • The A/E Initiated? Conditional checks if the role of the Process Initiator was A/E Lead or Consultant.
  • If True (Yes) the next step is PSA Mail Merge
  • If False (No) the next step is PSA MM (for A/E man

Toggle Cloak
PM Enters Release

Cloak
  • The Project Manager adds the appropriate release from the 05.02.05 MDA Release(s) folder of project 11112, and fills out any required fields.
  • If Submit is chosen the next step is Program Manager Review MDA
  • If Revise is chosen the next step is Initiator Revise MDA
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
Program Manager Review MDA

Cloak
  • The Program Manager reviews the Master Design Agreement Release details
  • If Submit is chosen the next step is Vendor Signature
  • If Revise is chosen the next step is Initiator Revise MDA

Toggle Cloak
Contracts Group

Cloak
  • The Contract Admin reviews the Master Design Agreement Release details, makes any changes and if necessary re-uploads the document in the PSA/MDA for Signature field.
  • If Submit is chosen the next step is Program Manager Review MDA
  • If Revise is chosen the next step is Initiator Revise MDA
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
Initiator Revise MDA

Cloak
  • The Initiator Revise MDA step allows the Process Initiator to make changes and resubmit the process.
  • If Resubmit is chosen the next step is MDA Release
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
Initiator Reviews Release

Cloak
  • The Initiator Reviews Release step allows the Process Initiator to make changes and resubmit the process.
  • If Submit is chosen the next step is Contracts Sends Release to Vendor

Toggle Cloak
Contracts Sends Release to Vendor

Cloak
  • The Contracts Sends Release to Vendor step allows the Contracts Admin to make send the release to the vendor.
  • If Submit is chosen the next step is Vendor Signature.
  • If Revise is chosen the next step is Initiator Reviews Release.

Toggle Cloak
Utilities PO?

Cloak
  • The Utilities PO? Conditional step allows the determines if the Program Type is Utilities.
  • If True (Yes) the next step is Est Fin cont>$1M
  • If False (No) the next step is Campus Construction?

Toggle Cloak
 Vendor Signature

Cloak
  • The Consultant, A/E Lead and/or the Project Manager takes the appropriate action to sign the document.
  • If Submit is chosen the next step is Program Manager Review MDA
  • If Revise is chosen the next step is Initiator Revise MDA

Toggle Cloak
PO CO MM

Cloak
  • The PO CO MM step is a mail merge automation step that completes the Phased Purchase Order Release mail merge document.
  • The next step is PM Attaches Contract

Toggle Cloak
Init PM Threshold

Cloak
  • The Init PM Threshold Conditionalchecks if the Change Amount of the PSA reaches the threshold that requires a Contract.
  • If True (Yes) the next step is PM Attaches Contract/ Reviews POCO MM
  • If False (No) the next step is PM Reviews POCO MM

Toggle Cloak
PM Attaches Contract/ Reviews POCO MM

Cloak
  • The Project Manager should attach the contract for the work of the PO that the PSA is modifying at this step.
  • If Submit is chosen the next step is PS for CC Director
  • If Redo PO CO MM is chosen the next step is PO CO MM

Toggle Cloak
PM Reviews POCO MM

Cloak
  • The Project Manager reviews the POCO MM.
  • If Submit is chosen the next step is PS for CC Director
  • If Redo PO CO MM is chosen the next step is PO CO MM

Toggle Cloak
OGC Counsel Reviews

Cloak
  • In this step the OGC Counsel reviews the information that has been entered to the process.
  • If Reviewed is chosen the next step is PM Review PSA - Manual Sig Req
  • If Revise is chosen the next step is Contracts Review PSA MM send from PM

Toggle Cloak
Contracts Review PSA MM send from PM

Cloak
  • In this step the Contracts Group reviews the information that has been entered to the process.
  • If Submit is chosen the next step is PM Review PSA - Manual Sig Req
  • If Revise is chosen the next step is PM Review MM
  • If Send to OGC is chosen the next step is OGC Council Review

Toggle Cloak
PM Review MM

Cloak
  • The Project Manager reviews the PSA Mail Merge.
  • If Submit is chosen the next step is Contracts Review PSA MM send from PM
  • If Revise is chosen the next step is PO CO MM

Toggle Cloak
PS for CC Director

Cloak
  • This automation step notifies the CC Director of the PO Release.
  • The next step is Program Manager reviews PO

Toggle Cloak
PM Attaches Contract

Cloak
  • The Project Manager attaches a copy of the vendor executed contract, and fills out the PM Description of Change (Internal Only) field if necessary.
  • The next step is Program Manager Reviews PO

Toggle Cloak
Program Manager Reviews PO

Cloak
  • The Program Manager reviews the Phased Purchase Order Release details.
  • If Reviewed is chosen the next step is OCP?
  • If Revise is chosen the next step is Initiator Revise PO Release

Toggle Cloak
OCP?

Cloak
  • The OCP? Conditional checks if the Program Type of the project is OCP
  • If True (Yes) the next step is OCP Director Approval
  • If False (No) the next step is CC Director Approval

Toggle Cloak
CC Director Approval

Cloak
  • The CC Director takes the appropriate action to approve the document.
  • If Submit is chosen the next step is SAP Hold Step
  • If Revise is chosen the next step is Initiator Revise PO Release

Toggle Cloak
OCP Director Approval

Cloak
  • The OCP Director takes the appropriate action to approve the document.
  • If Submit is chosen the next step is SAP Hold Step
  • If Revise is chosen the next step is Initiator Revise PO Release

Toggle Cloak
Initiator Revise PO Release

Cloak
  • The Initiator Revise PO Release step allows the Process Initiator to make changes and resubmit the process.
  • If Resubmit is chosen the next step is MDA Release
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
PSA Mail Merge

Cloak
  • The PSA Mail Merge step is a mail merge automation step that completes the Standard PSA mail merge document.
  • The next step is Project Manager Review

Toggle Cloak
PSA MM (for A/E man

Cloak
  • The PSA MM (for A/E man step is a mail merge automation step that completes the Standard PSA mail merge document to be sent to the A/E Lead or Consultant for a manual signature.
  • The next step is PM Attaches Contract

Toggle Cloak
Project Manager Review

Cloak
  • The Project Manager reviews the PSA Details and fills out all required fields.
  • If Submit is chosen the next step is Contracts Group Review PSA
  • If Revise is chosen the next step is Initiator Revise PSA

Toggle Cloak
Contracts Group Review PSA

Cloak
  • The Contract Admin and Contract Admin Manager review the PSA Details and determine whether or not it meets the requirements for OGC Counsel Review.
  • If Reviewed is chosen the next step is Vendor Signs
  • If Send to OGC is chosen the next step is OGC Counsel Review
  • If Revise is chosen the next step is Initiator Revise PSA

Toggle Cloak
OGC Counsel Review

Cloak
  • The DOF General Counsel reviews the PSA Details.
  • If Reviewed is chosen the next step is Vendor Signs
  • If Revise is chosen the next step is Contracts Group Review PSA

Toggle Cloak
Vendor Signs

Cloak
  • The Process Initiator takes the appropriate action to sign the document.
  • If Submit is chosen the next step is Additional Funding?
  • If Revise is chosen the next step is Initiator Revise PSA

Toggle Cloak
PM Review PSA - Manual Req

Cloak
  • The Project Manager fills out all required fields and sends the PSA Document to the Vendor for a manual signature.
  • If Submit is chosen the next step is Hold for Signed PSA
  • If Revise is chosen the next step is Initiator Revise PSA
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
Hold for Signed PSA

Cloak
  • The Project Manager and Contract Admin until they receive back the vendor manually signed PSA document and upload it to the process.
  • The next step is Additional Funding?

Toggle Cloak
Additional Funding?

Cloak
  • The Additional Funding? Conditional checks if Yes was selected for the Additional Project Funding? field.
  • If True (Yes) the next step is Spawn Budget Change (03.03)
  • If False (No) the next step is Program Manager Review

Toggle Cloak
Spawn Budget Change (03.03)

Cloak
  • This step spawns a 03.03 - Contingency Request / True-Up Form / Additional Funding Request (BCHNG) process.
  • The next step is CRSP Admin Mgr. Hold

Toggle Cloak
CRSP Admin Mgr. Hold

Cloak
  • The CRSP Admin holds the process in this step until additional funding has been applied to the project in both e-Builder and SAP.
  • The next step is Program Manager Review

Toggle Cloak
Program Manager Review

Cloak
  • The Program Manager reviews the vendor signed document in the PSA/MDA for Signature field.
  • If Submit is chosen the next step is Campus Construction?
  • If Revise is chosen the next step is Initiator Revise PSA

Toggle Cloak
Initiator Revise PSA

Cloak
  • The Initiator Revise PSA step allows the Process Initiator to make changes and resubmit the process.
  • If Resubmit is chosen the next step is MDA Release
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
Campus Construction?

Cloak
  • The Campus Construction? Conditional checks if the Program Type of the project is Academic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal
  • If True (Yes) the next step is SP&T Program?
  • If False (No) the next step is OCP?

Toggle Cloak
OCP?

Cloak
  • The OCP? Conditional checks if the Program Type of the project is OCP
  • If True (Yes) the next step is EstFinCon> $500K
  • If False (No) the next step is CSM?

Toggle Cloak
CSM?

Cloak
  • The CSM? Conditional checks if the Program Type of the project is CSG or R&M
  • If True (Yes) the next step is EstFinCon> $5m?
  • If False (No) the next step is Utilities Program?

Toggle Cloak
Utilities Program?

Cloak
  • The Utilities Program? Conditional checks if the Program Type of the project is CUP - OPS or Utilities
  • If True (Yes) the next step is Est Fin Cont>$1M
  • If False (No) the next step is FEG Program

Toggle Cloak
FEG Program?

Cloak
  • The FEG Program? Conditional checks if the Program Type of the project is Energy or SEG
  • If True (Yes) the next step is FEG Director Review
  • If False (No) the next step is EstFinCon >$1M

Toggle Cloak
EstFinCon > $1M

Cloak
  • The EstFinCon > $1M Conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is EstFinCon>$10M
  • If False (No) the next step is Dir. Finance Execute

Toggle Cloak
SP&T Program?

Cloak
  • The SP&T Program? Conditional checks if the Program Type of the project is System Performance & Turn-over
  • If True (Yes) the next step is SPT Director Review
  • If False (No) the next step is EstFinCon >$10m

Toggle Cloak
EstFinCon> $500K

Cloak
  • The EstFinCon> $500K Conditional checks if >$500,000<=$1,000,000, >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is OCP Director Review
  • If False (No) the next step is OCP Director Execute

Toggle Cloak
EstFinCon>$5m?

Cloak
  • The EstFinCon>$5m? Conditional checks if >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is CSM Director Review
  • If False (No) the next step is CSM Director Execute

Toggle Cloak
Est Fin cont> $1M

Cloak
  • The Est Fin cont> $1M Conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is Utilities Director Review
  • If False (No) the next step is Utilities Director Execute

Toggle Cloak
SPT Director Review

Cloak
  • The SPT Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>$10M
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
OCP Director Review

Cloak
  • The OCP Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>$10M
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
CSM Director Review

Cloak
  • The M&U Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>$10M
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
FEG Director Review

Cloak
  • The SEG Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>$10M
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
Utilities Director Review

Cloak
  • The Utilities Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>$10M
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
Dir. Finance Execute

Cloak
  • By taking the Approved action at this step the Director of Finance and Administration is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2
  • If Send CC Director is chosen the next step is CC Director Review.

Toggle Cloak
EstFinCon>$10m

Cloak
  • The EstFinCon>$10m Conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is CC Director Review
  • If False (No) the next step is CC Director Execute

Toggle Cloak
CC Director Review

Cloak
  • The CC Director reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>10<=100mil
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
CC Director Execute

Cloak
  • By taking the Approved action at this step the CC Director is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
OCP Director Execute

Cloak
  • By taking the Approved action at this step the OCP Director is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
CSM Director Execute

Cloak
  • By taking the Approved action at this step the M&U Director is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
Utilitites Director Execute

Cloak
  • By taking the Approved action at this step the Utilities Director is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
EstFinCon>$10M

Cloak
  • The EstFinCon>$10M Conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is Dir of Fin & Adm Review 2.
  • If False (No) the next step is Dir of Fin & Adm Review 1.

Toggle Cloak
Dir of Fin & Adm Review 1

Cloak
  • The Director of Finance and Administration reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is VP, CSS Execute.
  • If Revise is chosen the next step is Initiator Revise 2.
  • If Send CC Director is chosen the next step is CC Director Review.

Toggle Cloak
Dir of Fin & Adm Review 2

Cloak
  • The Director of Finance and Administration reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is VP, CSS Review.
  • If Revise is chosen the next step is Initiator Revise 2.
  • If Send CC Director is chosen the next step is CC Director Review.

Toggle Cloak
VP, CSS Review

Cloak
  • The VP for Campus Services and Stewardship reviews the Process Details and the appropriate file in the Change Order Document Details section.
  • If Submit is chosen the next step is EstFinCon>10<=100mil
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
VP, CSS Execute

Cloak
  • By taking the Approved action at this step the Deputy EVP is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
EstFinCon>10<=100mil

Cloak
  • The EstFinCon>10<=100mil Conditional checks if >$10,000,000<=$100,000,000 was selected for the Estimated Final Contract Amount field.
  • If True (Yes) the next step is VP Finance Execute
  • If False (No) the next step is EVPT Execute

Toggle Cloak
VP Finance Execute

Cloak
  • By taking the Approved action at this step the VP for Finance is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
EVPT Execute

Cloak
  • By taking the Approved action at this step the EVP&T Office is Approving the process.
  • If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
  • If Revise is chosen the next step is Initiator Revise 2

Toggle Cloak
Initiator Revise 2

Cloak
  • The Initiator Revise 2 step allows the Process Initiator to make changes and resubmit the process.
  • If Resubmit is chosen the next step is MDA Release
  • If Void is chosen the next step is Finish and the process is set to a Void status.

Toggle Cloak
Amendment Signature

Cloak
  • The Amendment Signature step is a e-Signature File Download automation step that completes the Docusign envelope.

  • The next step is SAP Hold Step

Toggle Cloak
SAP Hold Step

Cloak
  • Hold step for SAP Processing.
  • Once processed the next step is the PO MM step.

Toggle Cloak
PO MM

Cloak
  • The PO MM step is a mail merge automation step that completes the PSA PO CO MM mail merge document.
  • The next step is Project Manager Review

Toggle Cloak
AA/Contracts Sends Exec-PSA to Vendor

Cloak
  • The Administrative Assistant and Contract Admin should review the documents attached to the process, and send the executed documents to the vendor.
  • The next step is Finish.

Toggle Cloak
Finish

Cloak