Process

Status/Current Risks

Attachments

Initiate

  • 0-budget project limits product selection
  • Cost/Benefit is anecdotal, based on team background and experience, increases to efficiency unmeasured going into the project.
  • buyBuy-in from other teams to use their systems as proof-of-concept still pending

CfgMmgtProjectStartupChecklist.pdfDaptiv Project Profile

Prepare

  • Scope deliverable complete but milestone planning still insufficient
  • Risks need better defintion

Project Scope

Planning and Resource Allocation

  • End date still undetermined, planning still in process.
  • SAIS is still considering participation in the project and timeframe for participation.

Daptiv Project Home
Business Requirements \\

Track and Control

  • Jira tasks unpopulated

Daptiv Project PlanTasks and Milestones

Reporting



Review



Completion and Assessment



...