Project Request (Before Business Case Submission)

Project Start-up

Ongoing Project Forecasting

Prior to all Business Case submissions (internal projects
and
external submission to sponsors) an SAIS Project
Cost
Template must be completed and submitted to
SAIS Finance. 
All submitted Business Cases must
use the submitted
SAIS Project Cost Template. 
Once completed send SAIS
Project Cost Template
to sais-finance@mit.edu. It is
recommended that
all Project Managers set up an in-person
meeting with
SAIS Finance to discuss assumptions and issues.

SAIS Project Cost Template must include:

  • List of Resources (Internal & External)
  • Estimated Hours on Project for each Resource Type
  • Estimated Other Costs (Hardware, Software,Etc.)
  • Estimated Ongoing Support

 

 

...