This folder contains current copies of relevant project schedules.  These schedules are attached in MSProject format an presented in HTML format.

High Level Plan for SAPBiz 10-822-08 v4 (last updated 14 Oct 2008)

----| Project Start:
Project Finish: | Project Start Date: Sat 9/20/08
Project Finish Date: Tue 12/23/08

...

|

Tasks

...

 

ID

Task _ Name

Duration

Start _Date

Finish _Date

Predecessors

Resource _ Names

% Complete

1

2008 Support Pack Implementation Project

65 days

Mon 9/22/08

Tue 12/23/08

  

0%

2

Project Prep

33 30 days

Mon 9/22/08

Thu 11 Fri 10/631/08

  

0%

3

PS1 Snapshot at end of day

0 days

Mon 9/22/08

Mon 9/22/08

  

0%

4

Transaction list available

0 days

Fri 9/26/08

Fri 9/26/08

  R3 R3

0%

5

Identify test scenarios / transactions

5 days

Mon 9/29/08

Fri 10/3/08 4

BUS,BA

0%

6

Review and update test scripts

20 days

Mon 10/6/08

Fri 10/31/08 5

BUS,BA

0%

7

SF3 Unavailable at end of day

0 days

Fri 10/10/08

Fri 10/10/08

  

0%

8

PS1 snapshot at end of day

0 days

Mon 10/20/08

Mon 10/20/08

  R3 R3

0%

9

Execute Trial balance for snapshot

0.5 days

Mon 10/20/08

Mon 10/20/08

8 BUS BUS

0%

10

Save data warehouse extracts

0 days

Fri 10/10/08

Fri 10/10/08

7 DWH DWH

0%

11

Support packs available from SAP

0 days

Mon 10/20/08

Mon 10/20/08

  

0%

12

PS1 Import 1

0 days

Thu 10/23/08

Thu 10/23/08

  

0%

13

PS1 Import 2

0 days

Thu 10/30/08

Thu 10/30/08

 

 

14

PS1 Import 3

0 days

Thu 11/6/08

Thu 11/6/08

 

 

15

SF3 System Refresh

5 days

Tue 10/14/08

Mon 10/20/08

  

0%

16 14

Refresh with 9/22/08 PS1 Snapshot

2 days

Tue 10/14/08

Wed 10/15/08

  R3 R3

0%

17 15

R3 Action Log

0.5 days

Thu 10/16/08

Thu 10/16/08 16

R3 R3

0%

18 16

Scramble sensitive data

2.5 days

Thu 10/16/08

Mon 10/20/08

17 R3 R3

0%

19 17

PS1 Snapshot at end of day

0 days

Mon 10/20/08

Mon 10/20/08

  

0%

20 18

Execute Trial Balance for later comparison

0.5 days

Mon 10/20/08

Mon 10/20/08

19 R3 R3

0%

21 19

Support Packs available from SAP

0 days

Mon 10/20/08

Mon 10/20/08

  

0%

22 20

SFK Update

4 days

Tue 10/21/08

Fri 10/24/08

  

0%

23 21

Import Updates

1 day

Tue 10/21/08

Tue 10/21/08

21FS+1 day

R3

R3

0%

22 24

Identify and resolve import issues

1 day

Wed 10/22/08

Wed 10/22/08

23 R3 R3

0%

25 23

Validate security infrastructure (SNC)

1 day

Thu 10/23/08

Thu 10/23/08

24 R3 R3

0%

26 24

Validate SAPGui interactions

0.5 days

Fri 10/24/08

Fri 10/24/08

25 R3 R3

0%

27 25

Validate basic SAP functions work

0.5 days

Fri 10/24/08

Fri 10/24/08

R3

0%

26

PS1 Import - regular import cycle

0 days

Thu 10/23/08

Thu 10/23/08

 

0%

27

R3

28

SF3 Update

5 days

Mon 10/27/08

Fri 10/31/08

  

0%

29 28

Import Updates

2 days

Mon 10/27/08

Tue 10/28/08

21,27 R3 R3

0%

30 29

Execute action log

0.5 days

Wed 10/29/08

Wed 10/29/08

29

DEV,BA

0%

31 30

Update action log as necessary

0.5 days

Wed 10/29/08

Wed 10/29/08

 

DEV,BA

0%

31 32

Produce collision report

0.5 days

Wed 10/29/08

Wed 10/29/08 29

R3 R3

0%

33 32

Review collision report

1 day

Wed 10/29/08

Thu 10/30/08

32

DEV,BA

0%

34 33

Reimplement MIT mods

1 day

Thu 10/30/08

Fri 10/31/08

33 DEV DEV

0%

35 34

Confirm configuration steps work

0.5 days

Fri 10/31/08

Fri 10/31/08

34

DEV,BA

0%

35

Production Imports (last regular import cycle)

0 days

Thu 10/30/08

Thu 10/30/08

 

0%

36

Development slowdown starts

0 days

Fri 10/31/08

Fri 10/31/08

 

0%

37

Unit Test Preparation and Execution

6 days

Mon 11/3/08

Mon 11/10/08

  

0%

37 38

Apply support packs to SF2

2 days

Mon 11/3/08

Tue 11/4/08

35 R3 R3

0%

38 39

Update and Execute action log

0.5 days

Wed 11/5/08

Wed 11/5/08

37

BA,DEV

0%

40 39

Import transports from SF3

0.5 days

Wed 11/5/08

Wed 11/5/08

38 R3 R3

0%

40 41

Unit test, resolution and retest in SF2

3 days

Thu 11/6/08

Mon 11/10/08

39

BA,DEV

0%

41 42

System Test / User Acceptance Test Environment Preparations

10 days

Mon 10/27/08

Fri 11/7/08

  

0%

42 43

Refresh TST with 10/20 snapshot, NO SCRAMBLING DATA

3 days

Mon 10/27/08

Wed 10/29/08

  R3 R3

0%

43 44

Import post snapshot production transports (delta from 10/20 to 10/30)

2 days

Thu 10/30/08

Fri 10/31/08

42 R3 R3

0%

44 45

Import updates

2 days

Mon 11/3/08

Tue 11/4/08

43 R3 R3

0%

45 46

Import SF3 transports & post-update DEV transports (to be tested during SI & UAT)

1 day

Wed 11/5/08

Wed 11/5/08

44 DEV DEV

0%

46 47

Execute trial balance and compare with TB from 10/20

0.5 days

Thu 11/6/08

Thu 11/6/08

44,45 BUS BUS

0%

47 48

Execute action log

0.5 days

Thu 11/6/08

Thu 11/6/08

46

DEV,BA

0%

49 48

Execute DWH extracts and comparison

1 day

Fri 11/7/08

Fri 11/7/08 47

DWH

49

Development slowdown starts

0 days

Fri 11/7/08

Fri 11/7/08

48

 

0%

50

Execute System Integration Tests

6 days

Wed 11/12/08

Wed 11/19/08

  

0%

51

HR-Payroll

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

0%

52

Logistics

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

0%

53

EHS

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

0%

54

Financial

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

0%

55

Execute User Acceptance Test (UAT)

15 days

Thu 11/20/08

Fri 12/12/08

  

0%

56

Payroll comparison (tasks and duration to be validated)

Execute UAT

9 3 days

Thu 11/20/08 Mon 11

Thu 12/244/08

54 BUS BA,BUS

0%

57 Execute

UAT Financial Close

7 days

Tue 11/25/08 2 days

Fri 12/5/08 56

BUS

58

Financial Close

1 day

Mon 12/8/08

Mon 12/8/08

BUS

0%

58

57

BUS

59

Issue retesting

2 days

Tue 12/9/08

Wed 12/10/08

58 ALL ALL

0%

60 59

Execute another financial close?

1 day

Thu 12/11/08

Thu 12/11/08

59 BUS BUS

0%

61 60

UAT sign off

1 day

Fri 12/12/08

Fri 12/12/08

60 ALL ALL

0%

62 61

Cutover weekend & Controlled Start

2 days

Sat 12/13/08

Sun 12/14/08

61 ALL ALL

0%

63 62

Drop Dead Date for support packs in production

0 days

Mon 12/22/08

Mon 12/22/08

  

0%

64 63

First Calendar 2009 Payroll

0 days

Tue 12/23/08

Tue 12/23/08

 

0%