Support Pack 2008 User Acceptance Test

User Acceptance Testing (UAT) is a phase of software development in which the software is tested in the "real world" by the intended audience.

  

Important Dates 

11/20 to 12/10 - User acceptance testing

  • All testing done by 12/5
  • 12/8 - 12/10 for issue retesting and financial closing
  • Don't wait until the end to test

12/12 - Go / No Go Decision

  • Based on results of user acceptance testing
  • Business owners will indicate their approval and acceptance of testing

12/13 to 12/15 - Go live weekend 

  • Production will be down from 6pm Friday evening until 6am Monday morning

12/22 - Drop dead date for updating production with support packages

  • We have to be done by this date

12/23 - first 2009 payroll run