- 11/20 to 12/10 - User acceptance testing
- All testing done by 12/5
- 12/8 - 12/10 for issue retesting and financial closing
(- Don't wait until the end to test
) - 12/12 - Go / No Go Decision.
- Based on results of user acceptance testing
, - Business owners will indicate their approval and acceptance of testing
- 12/13 to 12/15 - Go live weekend. weekend
- Production will be down from 6pm Friday evening until 6am Monday morning
- 12/22 - Drop dead date for updating production with support packages.
- We have to be done by this date
- 12/23 - first 2009 payroll run