  • 11/20 to 12/10 - User acceptance testing
    • All testing done by 12/5
    • 12/8 - 12/10 for issue retesting and financial closing
    (
    • Don't wait until the end to test
    )
  • 12/12 - Go / No Go Decision
    • Based on results of user acceptance testing
    ,
    • Business owners will indicate their approval and acceptance of testing
  • 12/13 to 12/15 - Go live weekend.  weekend 
    • Production will be down from 6pm Friday evening until 6am Monday morning
  • 12/22 - Drop dead date for updating production with support packages
    • We have to be done by this date
  • 12/23 - first 2009 payroll run