  • update on sponsor
    • Steve Gass is on board
    • we will begin engaging with him in September to review where we are and next steps
  • review new way to look at the task list Impact Risk Resource Matrix
    • Oliver's matrix works
    • Patrick will transition the checklists under the impact, risk and resource levels accordingly
    • this easily translates into the decision making guide
  • plan for MTS presentation
    • outline of talking points:
      • define what we mean by release
      • describe issues we are trying to solve (high level)
      • outline where we started (desktop)
      • review deliverables (checklists matrix)
      • talk about next steps
      • review what will need going forward to implement these processes
    • Pat will flesh out the talking points by EOB Wednesday
    • Chris will take a shot at simplifying the release ball diagram to show what we will need in the future SWRecs.pdf SWRecsDetail.pdf
    • no PowerPoint deck - this will be a 1-2 page hand out
    • Pat and Patrick have volunteered to lead the presentation with participation from the team

...