Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Now - October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
  • 10/18/2010 - End of day production snapshot to be used to refresh test environments (a)
  • 11/01/2010 - Development Freeze begins
  • 11/1009/2010 - Last date to implement support & enhancement changes until freeze ends on 12/15/2010
  • 11/04/2010 - 11/10/2010 Unit test
  • 11/11/2010 - 12/10/2010 System Integration Test (b)
  • 12/10/2010 - 12/12/2010 Go-live weekend
  • 12/15/2010 - Development Freeze ends

...