- Unit test db - ready for use by test coordinators
- System preparation
- SF7 will be used for (1) a practice system and (2) source system for GUI user exit updates
- Ancillary system updates
- Solution manager (SPS24 - complete through production)
- Portal target SPS7
- PI w/ ADS target SPS7
- PS1 snapshot scheduled for tonight (10/04/2010) to be used to refresh SF3
- QC
- HRP domain has been set up
- Additional licenses have been installed
- File attachment issues have been resolved
- Need to load in production validations steps
- Risks Update
- EL went live!
- eW2 moved forward to 10/21
- OE still scheduled for 10/21
09/27/2010 - Core Team Meeting
...