Presentations
Meeting Notes
...
10/12/2010 - Core Team Meeting
In attendence: core team members
Updates
- System Preparation
- SF3 is now off line and being refreshed in preparation of Support Pack Application
- SF8 is now the system for the application of OSS notes for production support
- Request to review Action Log
- SF7 being used as a practice system and the system for Logon development work
- Test Planning
- Unit test planning
- In progress - extended due date to 10/15
- "Z" drive mapping needed for access to unit test db (see Rich for access)
- Reporting needed
- matrix report
- list of what's being tested for publication
- SIT test planning
- Extended due date to 10/25
- Basic structures have been agreed to
- User groups have been shown QC
- Automated test cases need to be validated/modified for HRP (in-progress)
- HRP waiting on EL cases
- Goal is to publish test plan at 10/27 SAPbiz meeting
- QC license restriction becoming a concern again (turns out we do not have unlimited view access)
- SAP SP release scheduled for 10/14 is on track/Application scheduled to begin in SFK on Monday 10/18
10/04/2010 - SP Steering Committee
...