10/19/2010 - Core Team Meeting
In attendence: core team members
Updates
- System Preparation
- SF3 has been refreshed; refreshed action log execution on schedule
- SF3 payroll simulation run on schedule
- SF7 practice system still being built (missing a patch level)
- this system will be used to develop gui logon changes
- Support Pack side effects report has been generated and posted to the Project Scope page of this wiki
- SFK Support Pack Application process has begun
- Support Application process will begin in SF3 starting next Monday
- Test Planning
- Unit Test
- for the most part 2009/2010 comparisons are complete
- new transaction review is in process
- Rich is working on additional query requests (though off-site this week)
- SIT
- needs to be wrapped up by 10/25
- Actively in progress
- Goal is to communicate test plans at SAPbiz
- Transport management
- Updated list is has been posted on the wiki
- Many of the transports on the list are obsolete
- Several projects are going live this week so the list will significantly drop down
10/12/2010 - Core Team Meeting
...