Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Unit Testing

...

Dates 

11/04/2010 - 11/10/2010 - Unit Test Execution in the Development Environment (SF2)

Plans

2010 Unit Test Plan - FIN.xlsx
2010 Unit Test Plan - HRP.xlsx

...

System Integration Testing

...

Dates

 11 11/11/2010 - 12/09/2010 - System Integration Test Execution in the SAP Project Testing & QA Environment (SH3)

  • 11/11/2010 - 11/17/2010 - Payroll comparison runs (Oct/2010 runs - limited system access)
  • 11/18/2010 - 11/18/2010 - Controlled Financial Close (Oct/2010 - limited system access)
  • 11/19/2010 - 12/05/2010 - General System Integration Testing (open to all testers - 9 business days)
  • 12/06/2010 - 12/06/2010 - Controlled Financial Close (Nov/2010 - limited system access)
  • 12/07/2010 - 12/08/2010 - Retest any open issues
  • 12/08/2010 - 12/08/2010 - Validation step test
  • 12/09/2010 - 12/09/2010 - Test Review/Sign-off

...