Project Organization

  • Steering Committee
    • - Based on feedback from last years Support Pack Project the Steering Committee was expanded in include more BPO representation.
    • - The general consesus was this was a good idea as in prior years BPO representation was inadequate.
  • Core Team
    • - Worked well; representation was adequate.
    • - Testing coordinators made organizing work easier.
    • - QA representation (a point person) on the team proved beneficial to the QA team and the project as a whole.
  • Functional Areas (testing coordinators)

...