- Steering Committee
- - Based on feedback from last years Support Pack Project the Steering Committee was expanded to include more BPO representation.
- - The general consesus was this was a good idea as in prior years BPO representation was inadequate.
- - Should create an email list for committee members.
- Core Team
- - Worked well; representation was adequate.
- - Testing coordinators made organizing work easier.
- - QA representation (a point person) on the team proved beneficial to the QA team and the project as a whole.
- - Transport coordinator continues to play an important role.
...
- Adequate for the project
- Validation by BPO should be tested before cutover weekend (some testers where not the normal executers or the transactions being tested)
- Remote cutover testers should test connections to system before cutover weekend
Testing
- Unit Testing
- SIT/UAT Testing
...
- Communication
- The Plan itself
- emails- Subscribe to email list of core team during the project/during cutover (watcher list could be added)** phone
- conference line - use WebEx to allow more participants on the call
- validation steps
- Execution
- Other
- Communication of Sunday attendance should be communicated earlier in the project to allow staff more time to plan ahead
-
...