Month | Major Deliverables | Responsible |
|---|
September | - Plan project, resources, kickoff
- QA instructions, templates
- Update test scripts, catalog
- Move pending work to production
| - Frank Quern
- Wendy Bastos
- QA Team, Functional Test Coordinators
- Extended Functional Teams
|
October | - System preparation
- Continue moving pending work to production
- Complete test plan
| - Technical Core Team
- Extended Functional Teams
- QA, Functional Test Coordinators
|
November | - Unit test
- Start SIT
| - Extended functional team members
- Extended Functional Team, Business Owners
|
December | - Complete SIT
- SP applied to Production
| - Extended Function Team, Business Owners
- All
|
Detailed Project Plan
...
SAP SP 2010_Project_Plan.mppunder contstruction ...
Page Notes
...
(a) The 10/18/2010 snapshot date is being used because it stages time data after its load and before evaluation, it right before the monthly and pension pay runs, it is relatively close to the freeze date minimizing the number of transports that will need to be imported into the test environment before execution of the SP application process.
...