Lessons learned notes (IS&T session held 02/01/2011)
Lessons learned notes (IS&T session held 01/28/2011)
Project Organization
...
- Communication
- The Plan itself - well documented, easy to follow, clear as to who was doing what and when.
- emails- Subscribe to email list of core team during the project/during cutover (watcher list could be added)
- status phone - was used throughout the weekend by IS&T staff
- conference line - use WebEx to allow more participants on the call
- validation steps
- Execution
- For the most part ran smoothly - went live slightly ahead of schedule
- Cutover plan contained necessary details for successful execution
- Other
- Expectation of Sunday attendance by IS&T staff should be communicated earlier in the project to allow staff more time to plan ahead